Construction of CC Road from Palton Hembram house to AWC at Khuntapal
OD/365/3505/120321/390129/00038229
5th SFC Grant in Aid
All Weather Connectivity
Road
CC Road
28788
22-10-2025
Download
dfgdsfdsfs

Mayurbhanj
Rasgovindpur
Khuntapal

Stage wise Geo-tag Photo:

Before
Status Image
  • Latitude: 21.7868249
  • Longitude: 87.0058189
  • Date & Time: 17 Jan 2026, 09:23 AM
Transparency Board
Status Image
  • Latitude: 21.7868125
  • Longitude: 87.0055341
  • Date & Time: 17 Jan 2026, 09:23 AM
During
Status Image
  • Latitude: 21.7868095
  • Longitude: 87.0053498
  • Date & Time: 17 Jan 2026, 09:23 AM
Completed
Status Image
  • Latitude: 21.7868238
  • Longitude: 87.0054735
  • Date & Time: 17 Jan 2026, 09:23 AM

200000
199968.00
32
Download

Stage Officer Date Started Date Completed Status
Case Record Opened ANANTA KUMAR HANSDA (BDO) 15-11-2025 15-11-2025 Approved
Estimate Preparation ANANTA KUMAR HANSDA (BDO) 15-11-2025 07-12-2025 Approved
Technical Sanction ANUPAM PRAKASH BEHERA (AEE) 07-12-2025 08-12-2025 Approved
Administrative Approval ANANTA KUMAR HANSDA (BDO) 08-12-2025 09-12-2025 Approved
Work Order Issued ANANTA KUMAR HANSDA (BDO) 09-12-2025 09-12-2025 Generated
Execution In Progress DIPAK KUMAR MURMU (AE / JE) 09-12-2025 10-01-2026 Approved