CONSTRUCTION OF CC ROAD FROM JUANGA SAHI TO PRAMOD HOUSE
OD/361/3444/119268/386312/00040405
5th SFC Grant in Aid
All Weather Connectivity
Road
CC Road
28788
22-10-2025
Download
dfgdsfdsfs

Kendujhar
Bansapal
Gonasika

Stage wise Geo-tag Photo:

Before
Status Image
  • Latitude: 21.4845524
  • Longitude: 85.519245
  • Date & Time: 27 Jan 2026, 02:50 PM
Transparency Board
Status Image
  • Latitude: 21.4844636
  • Longitude: 85.5191107
  • Date & Time: 02 Feb 2026, 02:01 PM
During
Status Image
  • Latitude: 21.4845541
  • Longitude: 85.5196439
  • Date & Time: 02 Feb 2026, 03:22 PM
Completed
Status Image
  • Latitude: 21.4844852
  • Longitude: 85.5192261
  • Date & Time: 03 Feb 2026, 02:08 PM

143803
0
143803
Download

Stage Officer Date Started Date Completed Status
Case Record Opened KendujharBansapalBDO (BDO) 07-11-2025 10-11-2025 Approved
Estimate Preparation KendujharBansapalBDO (BDO) 10-11-2025 01-12-2025 Approved
Technical Sanction Monalisha behera (AEE) 01-12-2025 03-12-2025 Approved
Administrative Approval KendujharBansapalBDO (BDO) 03-12-2025 03-12-2025 Approved
Work Order Issued KendujharBansapalBDO (BDO) 03-12-2025 03-12-2025 Generated
Execution In Progress BALAI TUDU (AE / JE) 03-12-2025 02-02-2026 Approved