Improvement of road at Smasan Road at Madhusudanpur
OD/354/3380/117901/411594/00052581
5th SFC Grant in Aid
All Weather Connectivity
Road
Pavor Block
29143
10-12-2024
Download
dfgdsfdsfs

Ganjam
Polosara
Bellagam

Stage wise Geo-tag Photo:

Before
Status Image
  • Latitude: 19.7122883
  • Longitude: 84.8036817
  • Date & Time: 22 Sep 2025, 03:45 PM
Transparency Board
Status Image
  • Latitude: 19.7121944
  • Longitude: 84.8036598
  • Date & Time: 22 Sep 2025, 03:45 PM
During
Status Image
  • Latitude: 19.7120902
  • Longitude: 84.8036529
  • Date & Time: 22 Sep 2025, 03:45 PM
Completed
Status Image
  • Latitude: 19.7121542
  • Longitude: 84.8035629
  • Date & Time: 22 Sep 2025, 03:45 PM

210000
209998.00
2
Download

Stage Officer Date Started Date Completed Status
Case Record Opened SASI BHUSAN MAHAPATRO (BDO) 15-09-2025 15-09-2025 Approved
Estimate Preparation SASI BHUSAN MAHAPATRO (BDO) 15-09-2025 20-09-2025 Approved
Technical Sanction Laxmi Narayan Pattanayak (AEE) 20-09-2025 20-09-2025 Approved
Administrative Approval SASI BHUSAN MAHAPATRO (BDO) 20-09-2025 20-09-2025 Approved
Work Order Issued SASI BHUSAN MAHAPATRO (BDO) 20-09-2025 20-09-2025 Generated
Execution In Progress Sradhanta Prasad Sahu (AE / JE) 20-09-2025 20-09-2025 Approved