Final Dpr

State: Odisha District: Nayagarh Block: Nayagarh Gram Panchayat: Champatipur
Work Code: OD/367/3527/120660/406280/00014227 (CONST OF ROAD & CULVERT CHAMPATIPUR NEAR MAHIMA ASHRAM SCHOOL)
Project Category: Road
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Nayagarh Bill Status: 1st Bill
Proposal Date: 17-11-2023 Date of Commencement: 27-04-2025
Date of Completion: - Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Jyotishree Subudhi
Administrative Approval Details
Approval No.: OD/367/3527/120660/406280/00014227/AS
Technical Sanction Details
Technical Sanction No.: OD/367/3527/120660/406280/00014227/TS
Fund Sanction No.: 446
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 11.25 779.535372 8769.772935
2 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 11.25 5130.2318043 57715.107798375
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 11.2338 6905.5061581 77575.075078864
Total Amount (in Rs.): 144059.95581224
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
Rs. 452 Rs. 552
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.25 Cubic Meter 0.1236 1.3905 - -
2 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.25 Cubic Meter 3.9 43.875 0.18 2.025
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.2338 Cubic Meter 4.6 51.67548 0.68 7.638984
Total Qty 96.94098 9.663984
Rate Per Man Day 452 552
Total Amount 43817.32296 5334.519168
Total Labour Amount (in Rs.): 49151.842128
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.25 Cum 1 11.25 - - - - - - - -
2 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.25 Cum - - 2.29 25.7625 0.48 5.4 0.96 10.8 - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.2338 Cum - - 3.23 36.285174 0.45 5.05521 - - 0.9 10.11042
Total Qty 11.25 62.047674 10.45521 10.8 10.11042
Rate Per Unit 410.7 579.287 417.13 1038.44 1672.63
Total Amount 4620.375 35943.410928438 4361.1817473 11215.152 16910.9918046
Total Material Amount (in Rs.): 73051.111480338
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.25 Cum 1 11.25 - - - - - - - -
2 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.25 Cum - - 2.29 25.7625 0.48 5.4 0.96 10.8 - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.2338 Cum - - 3.23 36.285174 0.45 5.05521 - - 0.9 10.11042
Total Qty 11.25 62.047674 10.45521 10.8 10.11042
Rate Per Unit 305.25 0 305.25 199.5 199.5
Total Amount 3434.0625 0 3191.4528525 2154.6 2017.02879
Total Royalty Amount (in Rs.): 10797.1441425
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 500 Rs. 500
Total Addition Component Amount (in Rs.): 500
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Royalty @ Rs. 3478.03695 Rs. 3478.03695
2 Additional Royalty @ Rs. 6797.40165 Rs. 6797.40165
3 EMF @ Rs. 173.9018475 Rs. 173.9018475
4 DMF @ Rs. 347.803695 Rs. 347.803695
5 Empty Gunny Bag (Cement x Gunny Bag Rate : 73 x 3.945) @ 493.125 Rs. 493.125
6 Labour Cess @ 1% Rs. 1445.5995581224
Total Deduction Component Amount (in Rs.): 12735.868700622
Total Net Amount (in Rs.): 131824.08711162