Final Dpr

State: Odisha District: Boudh Block: Boudh Gram Panchayat: Baunsuni
Work Code: OD/349/3329/116779/418274/00016782 (Improvement of road from NH-57 to Chhelibahal Road)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Boudh Bill Status: Final Bill
Proposal Date: - Date of Commencement: 23-03-2025
Date of Completion: 15-04-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: Ashutosh Behera
Administrative Approval Details
Approval No.: OD/349/3329/116779/418274/00016782/AS
Technical Sanction Details
Technical Sanction No.: OD/349/3329/116779/418274/00016782/TS
Fund Sanction No.: 28963
Fund Sanction Amount (in Rs.): 143788
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 3.909375 235.56432 920.9092635
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 9.15 514.258872 4705.4686788
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 13.059375 5361.4464684 70017.139973261
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 25.12 215.38264180804 5410.411962218
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 8.6925 6877.3025848 59780.952718374
Total Amount (in Rs.): 140834.88259615
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 452 Rs. 552 Rs. 502
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.909375 Cubic Meter 0.516 2.0172375 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.15 Cubic Meter 0.1236 1.13094 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.059375 Cubic Meter 3.9 50.9315625 - - 0.18 2.3506875
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 25.12 Square Meter - - 0.05 1.256 0.05 1.256
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.6925 Cubic Meter 4.6 39.9855 - - 0.68 5.9109
Total Qty 94.06524 9.5175875 1.256
Rate Per Man Day 452 552 502
Total Amount 42517.48848 5253.7083 630.512
Total Labour Amount (in Rs.): 48401.70878
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM104 BRM092 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.909375 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.15 Cum 1 9.15 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.059375 Cum - - 2.29 29.90596875 0.48 6.2685 0.96 12.537 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 25.12 Sqm - - - - - - - - 0.00267 0.0670704 0.126 3.16512 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.6925 Cum - - 3.23 28.076775 0.45 3.911625 - - - - - - 0.9 7.82325
Total Qty 9.15 57.98274375 10.180125 12.537 0.0670704 3.16512 7.82325
Rate Per Unit 413.05 556.782 678.39 1401.46 58620.646 276.666 1802.83
Total Amount 3779.4075 32283.748030612 6906.09499875 17570.10402 3931.7101754784 875.68108992 14103.9897975
Total Material Amount (in Rs.): 79450.735612261
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM104 BRM092 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.909375 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.15 Cum 1 9.15 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.059375 Cum - - 2.29 29.90596875 0.48 6.2685 0.96 12.537 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 25.12 Sqm - - - - - - - - 0.00267 0.0670704 0.000614 0.01542368 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.6925 Cum - - 3.23 28.076775 0.45 3.911625 - - - - - - 0.9 7.82325
Total Qty 9.15 57.98274375 10.180125 12.537 0.0670704 0.01542368 7.82325
Rate Per Unit 40.25 0 40.25 149.5 0 0 149.5
Total Amount 368.2875 0 409.75003125 1874.2815 0 0 1169.575875
Total Royalty Amount (in Rs.): 3821.89490625
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 1530 Rs. 1530
2 Contingency @ 1% Rs. 1408.3488259615
Total Addition Component Amount (in Rs.): 2938.3488259615
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ 1% Rs. 1437.7323142211
2 Royalty @ Rs. 3323.386875 Rs. 3323.386875
3 EMF @ Rs. 166.16934375 Rs. 166.16934375
4 DMF @ Rs. 332.3386875 Rs. 332.3386875
5 Empty Gunny Bag (Cement x Gunny Bag Rate : 63 x 3.945) @ 497.07 Rs. 497.07
6 Labour Cess @ 1% Rs. 1437.7323142211
Total Deduction Component Amount (in Rs.): 7194.4295346922
Total Net Amount (in Rs.): 136578.80188742