Final Dpr

State: Odisha District: Cuttack Block: Niali Gram Panchayat: Baharana
Work Code: OD/350/3341/117055/400341/00017368 (Imp of Road with CC Gr-II Metaling from Athantara Tareni Temple to Bandhu Biswal House Athantara)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Niali Bill Status: Final Bill
Proposal Date: 10-10-2024 Date of Commencement: 28-05-2025
Date of Completion: 25-06-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Diptiranjita Sahoo
Administrative Approval Details
Approval No.: OD/350/3341/117055/400341/00017368/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3341/117055/400341/00017368/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 590000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 104.7375 200.6466 21015.2232675
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 18.525 702.559232 13014.9097728
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 16.31625 6164.49788856 100581.48867422
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 3.49125 7687.71627472 26839.739444116
5 R.C.C. Work (AR0405Ab) : Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work, etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Plinth band) Cum 35.8974 7883.0863397313 282982.30357187
6 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. Qntl 15.645 8773.109268 137255.29449786
Total Amount (in Rs.): 581688.95922836
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 512 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 104.7375 Cubic Meter 0.43 45.037125 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.525 Cubic Meter 0.1236 2.28969 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 16.31625 Cubic Meter 3.9 63.633375 - - 0.18 2.936925 - -
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.49125 Cubic Meter 4.6 16.05975 - - 0.68 2.37405 - -
5 R.C.C. Work (AR0405Ab) : Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work, etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Plinth band) 35.8974 Cubic Meter 1.3333 47.86200342 0.3073 11.03127102 0.35 12.56409 - -
6 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 15.645 Quintal 0.8 12.516 0.044 0.68838 - - 0.3 4.6935
Total Qty 187.39794342 17.875065 11.71965102 4.6935
Rate Per Man Day 462 562 512 612
Total Amount 86577.84986004 10045.78653 6000.46132224 2872.422
Total Labour Amount (in Rs.): 105496.51971228
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM060 BRM052 BRM104 BRM092 BRM162 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) :.Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 104.7375 Cum - - - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.525 Cum 1 18.525 - - - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 16.31625 Cum - - 2.29 37.3642125 0.48 7.8318 0.96 15.6636 - - - - - - - - - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.49125 Cum - - 3.23 11.2767375 0.45 1.5710625 - - 0.9 3.142125 - - - - - - - - - - - -
5 R.C.C. Work (AR0405Ab) :.Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work, etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Plinth band) 35.8974 Cum - - 4.03333 144.786060342 0.45 16.15383 - - - - 0.36 12.923064 0.54 19.384596 0.01335 0.47923029 0.63 22.615362 - - - -
6 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 15.645 Qntl - - - - - - - - - - - - - - - - - - 0.8 12.516 1.05 16.42725
Total Qty 18.525 193.427010342 25.5566925 15.6636 3.142125 12.923064 19.384596 0.47923029 22.615362 12.516 16.42725
Rate Per Unit 543.25 569.712 548.19 2176.31 2604.91 2614.91 2556.21 58620.646 276.666 90.1 6492.532
Total Amount 10063.70625 110197.68891596 14009.923261575 34088.849316 8184.95283375 33792.64928424 49551.09814116 28092.789182567 6256.901743092 1127.6916 106654.446297
Total Material Amount (in Rs.): 402020.69682535
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM060 BRM052 BRM104 BRM092 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) :.Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 104.7375 Cum - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.525 Cum 1 18.525 - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 16.31625 Cum - - 2.29 37.3642125 0.48 7.8318 0.96 15.6636 - - - - - - - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.49125 Cum - - 3.23 11.2767375 0.45 1.5710625 - - 0.9 3.142125 - - - - - - - - - -
5 R.C.C. Work (AR0405Ab) :.Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work, etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Plinth band) 35.8974 Cum - - 4.03333 144.786060342 0.45 16.15383 - - - - 0.36 12.923064 0.54 19.384596 0.01335 0.47923029 0.00307 0.110205018 - -
6 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 15.645 Qntl - - - - - - - - - - - - - - - - - - 1.05 16.42725
Total Qty 18.525 193.427010342 25.5566925 15.6636 3.142125 12.923064 19.384596 0.47923029 0.110205018 16.42725
Rate Per Unit 95.25 0 95.25 158.5 158.5 158.5 158.5 0 0 0
Total Amount 1764.50625 0 2434.274960625 2482.6806 498.0268125 2048.305644 3072.458466 0 0 0
Total Royalty Amount (in Rs.): 12300.252733125
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 2350 Rs. 2350
2 Contingency @ Rs. 5900 Rs. 5900
Total Addition Component Amount (in Rs.): 8250
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 5900 Rs. 5900
2 Royalty @ Rs. 8187.5992875 Rs. 8187.5992875
3 Additional Royalty @ Rs. 2884.5135525 Rs. 2884.5135525
4 EMF @ Rs. 409.379964375 Rs. 409.379964375
5 DMF @ Rs. 818.75992875 Rs. 818.75992875
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 1530.66 Rs. 1530.66
7 Labour Cess @ Rs. 5900 Rs. 5900
8 Any Other Lumpsum Bill @ Rs. 11800 Rs. 11800
Total Deduction Component Amount (in Rs.): 37430.912733125
Total Net Amount (in Rs.): 552508.04649524