Final Dpr

State: Odisha District: Ganjam Block: Purushottampur Gram Panchayat: Ranajhali
Work Code: OD/354/3381/117943/412221/00017477 (CONST OF CC/PAVOR ROAD FROM LOKNATH BEHER GHARA CHAKA TO BHANDRI KOTHGURHA RANAJHALI)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Purushottampur Bill Status: Final Bill
Proposal Date: 12-10-2024 Date of Commencement: 19-05-2025
Date of Completion: 03-06-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: Pavor Block
Project Type: New Work Name of Executant: Janaki Patro
Administrative Approval Details
Approval No.: OD/354/3381/117943/412221/00017477/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3381/117943/412221/00017477/TS
Fund Sanction No.: 29143
Fund Sanction Amount (in Rs.): 538000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 6.0243992 200.6466 1208.7752165227
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 106.92518745161 481.237932 51456.456087925
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 13.465771072 6957.4853536 93687.905008371
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 91.71012548 216.23489289764 19830.929160797
5 miscellaneous (ARM287) : Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. Sqm 593.9310529302 620.9811 368819.95857275
Total Amount (in Rs.): 535004.02404637
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.0243992 Cubic Meter 0.43 2.590491656 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 106.92518745161 Cubic Meter 0.1236 13.215953169019 - - - -
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.465771072 Cubic Meter 4.6 61.9425469312 - - 0.68 9.15672432896
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 91.71012548 Square Meter - - 0.05 4.585506274 0.05 4.585506274
Total Qty 77.748991756219 13.74223060296 4.585506274
Rate Per Man Day 462 562 512
Total Amount 35920.034191373 7723.1335988635 2347.779212288
Total Labour Amount (in Rs.): 45990.947002525
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM056 BRM104 BRM092 BRMM287
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) :.Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.0243992 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 106.92518745161 Cum 1 106.92518745161 - - - - - - - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.465771072 Cum - - 3.23 43.49444056256 0.45 6.0595969824 0.9 12.1191939648 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 91.71012548 Sqm - - - - - - - - 0.00267 0.2448660350316 0.126 11.55547581048 - -
5 miscellaneous(ARM287) :.Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. 593.9310529302 Sqm 0.03 17.817931587906 - - - - - - - - - - 1 593.9310529302
Total Qty 124.74311903952 43.49444056256 6.0595969824 12.1191939648 0.2448660350316 11.55547581048 593.9310529302
Rate Per Unit 338.87 593.232 342.24 1672.63 58573.086 229.106 608.4
Total Amount 42271.700748921 25802.293963809 2073.8364712566 20270.927401343 14342.559328385 2647.4288410358 361347.65260273
Total Material Amount (in Rs.): 468756.39935748
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) :.Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.0243992 Cum - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 106.92518745161 Cum 1 106.92518745161 - - - - - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.465771072 Cum - - 3.23 43.49444056256 0.45 6.0595969824 0.9 12.1191939648 - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 91.71012548 Sqm - - - - - - - - 0.00267 0.2448660350316 0.000614 0.05631001704472
5 miscellaneous(ARM287) :.Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. 593.9310529302 Sqm 0.03 17.817931587906 - - - - - - - - - -
Total Qty 124.74311903952 43.49444056256 6.0595969824 12.1191939648 0.2448660350316 0.05631001704472
Rate Per Unit 80.5 0 80.5 289.75 0 0
Total Amount 10041.821082681 0 487.7975570832 3511.5364513008 0 0
Total Royalty Amount (in Rs.): 14041.155091065
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 2994 Rs. 2994
Total Addition Component Amount (in Rs.): 2994
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Royalty @ Rs. 6153.5902761911 Rs. 6153.5902761911
2 Additional Royalty @ Rs. 6964.5262734453 Rs. 6964.5262734453
3 EMF @ Rs. 307.67951380955 Rs. 307.67951380955
4 DMF @ Rs. 615.35902761911 Rs. 615.35902761911
5 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 343.215 Rs. 343.215
6 Labour Cess @ 1% Rs. 5379.9802404637
Total Deduction Component Amount (in Rs.): 19764.350331529
Total Net Amount (in Rs.): 518233.67371484