Final Dpr

State: Odisha District: Cuttack Block: Banki Gram Panchayat: Ostia
Work Code: OD/350/3334/116916/398888/00019903 (Imp. of Bhandari House to Village Mandap Road with CC/ Gr-II Metalling, Phulabadi)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Banki Bill Status: Final Bill
Proposal Date: 31-12-2024 Date of Commencement: 11-08-2025
Date of Completion: 20-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Repair and Maintenance Name of Executant: Sanjay Kumar Samal
Administrative Approval Details
Approval No.: OD/350/3334/116916/398888/00019903/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3334/116916/398888/00019903/TS
Fund Sanction No.: 1130
Fund Sanction Amount (in Rs.): 100000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 9.45 7534.79151822 71203.779847179
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 7 216.23489289764 1513.6442502835
3 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 6.75 240.77592 1625.23746
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 3.564 5994.44100706 21364.187749162
Total Amount (in Rs.): 95706.849306624
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.45 Cubic Meter 4.6 43.47 - - 0.68 6.426
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 7 Square Meter - - 0.05 0.35 0.05 0.35
3 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.75 Cubic Meter 0.516 3.483 - - - -
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.564 Cubic Meter 3.9 13.8996 - - 0.18 0.64152
Total Qty 60.8526 7.41752 0.35
Rate Per Man Day 462 562 512
Total Amount 28113.9012 4168.64624 179.2
Total Labour Amount (in Rs.): 32461.74744
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM056 BRM104 BRM092 BRM044
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.45 Cum 3.23 30.5235 0.45 4.2525 0.9 8.505 - - - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 7 Sqm - - - - - - 0.00267 0.01869 0.126 0.882 - -
3 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.75 Cum - - - - - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.564 Cum 2.29 8.16156 0.48 1.71072 - - - - - - 0.96 3.42144
Total Qty 38.68506 5.96322 8.505 0.01869 0.882 3.42144
Rate Per Unit 575.657 522.15 2282.91 58573.086 229.106 1854.31
Total Amount 22269.32558442 3113.695323 19416.14955 1094.73097734 202.071492 6344.4104064
Total Material Amount (in Rs.): 52440.38333316
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM056 BRM104 BRM092 BRM044
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.45 Cum 3.23 30.5235 0.45 4.2525 0.9 8.505 - - - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 7 Sqm - - - - - - 0.00267 0.01869 0.000614 0.004298 - -
3 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.75 Cum - - - - - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.564 Cum 2.29 8.16156 0.48 1.71072 - - - - - - 0.96 3.42144
Total Qty 38.68506 5.96322 8.505 0.01869 0.004298 3.42144
Rate Per Unit 0 386.15 158.5 0 0 158.5
Total Amount 0 2302.697403 1348.0425 0 0 542.29824
Total Royalty Amount (in Rs.): 4193.038143
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 3000 Rs. 3000
2 Contingency @ Rs. 1000 Rs. 1000
Total Addition Component Amount (in Rs.): 4000
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 1000 Rs. 1000
2 Royalty @ Rs. 1759.1499 Rs. 1759.1499
3 Additional Royalty @ Rs. 2170.015758 Rs. 2170.015758
4 EMF @ Rs. 87.957495 Rs. 87.957495
5 DMF @ Rs. 175.91499 Rs. 175.91499
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 17 x 3.945) @ 311.655 Rs. 311.655
7 Labour Cess @ Rs. 1000 Rs. 1000
Total Deduction Component Amount (in Rs.): 6504.693143
Total Net Amount (in Rs.): 93202.156163624