Final Dpr

State: Odisha District: Kandhamal Block: Baliguda Gram Panchayat: Sudra
Work Code: OD/359/3422/118879/416583/00026076 (IMPROVEMENT OF ROAD AT KATERIBHATTA)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Baliguda Bill Status: Final Bill
Proposal Date: 17-12-2024 Date of Commencement: 01-07-2025
Date of Completion: 10-07-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: CC Road
Project Type: New Work Name of Executant: BIJAYA KUMAR KISHAN
Administrative Approval Details
Approval No.: OD/359/3422/118879/416583/00026076/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3422/118879/416583/00026076/TS
Fund Sanction No.: 4605
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102a4) : Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift - Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. Cum 4.21360780032 219.77802 926.05837941088
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 10.42514706816 447.796832 4668.3478302561
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 18.04010092416 5122.3262414 92407.282361329
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 12.110529024 7234.3092038 87611.31158121
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 40.134096 216.23489289764 8678.3919501036
Total Amount (in Rs.): 194291.39210231
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a4) : Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift - Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 4.21360780032 Cubic Meter 0.471 1.9846092739507 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.42514706816 Cubic Meter 0.1236 1.2885481776246 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 18.04010092416 Cubic Meter 3.9 70.356393604224 - - 0.18 3.2472181663488
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 12.110529024 Cubic Meter 4.6 55.7084335104 - - 0.68 8.23515973632
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 40.134096 Square Meter - - 0.05 2.0067048 0.05 2.0067048
Total Qty 129.3379845662 13.489082702669 2.0067048
Rate Per Man Day 462 562 512
Total Amount 59754.148869584 7580.8644788999 1027.4328576
Total Labour Amount (in Rs.): 68362.446206084
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102a4) :.Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift - Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 4.21360780032 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.42514706816 Cum 1 10.42514706816 - - - - - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 18.04010092416 Cum - - 2.29 41.311831116326 0.48 8.6592484435968 0.96 17.318496887194 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 12.110529024 Cum - - 3.23 39.11700874752 0.45 5.4497380608 - - 0.9 10.8994761216 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 40.134096 Sqm - - - - - - - - - - 0.00267 0.10715803632 0.126 5.056896096
Total Qty 10.42514706816 80.428839863846 14.108986504397 17.318496887194 10.8994761216 0.10715803632 5.056896096
Rate Per Unit 346.01 575.422 548.19 1128.47 2128.33 58573.086 229.106
Total Amount 3607.205137054 46280.523892134 7734.4053118453 19543.404182291 23197.682013885 6276.5768769625 1158.5652369702
Total Material Amount (in Rs.): 107798.36265114
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102a4) :.Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift - Earthwork in hard soil or gravelly soil within 50m lead, with one extra lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 4.21360780032 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.42514706816 Cum 1 10.42514706816 - - - - - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 18.04010092416 Cum - - 2.29 41.311831116326 0.48 8.6592484435968 0.96 17.318496887194 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 12.110529024 Cum - - 3.23 39.11700874752 0.45 5.4497380608 - - 0.9 10.8994761216 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 40.134096 Sqm - - - - - - - - - - 0.00267 0.10715803632 0.000614 0.024642334944
Total Qty 10.42514706816 80.428839863846 14.108986504397 17.318496887194 10.8994761216 0.10715803632 0.024642334944
Rate Per Unit 40.25 0 40.25 149.5 149.5 0 0
Total Amount 419.61216949344 0 567.88670680197 2589.1152846354 1629.4716801792 0 0
Total Royalty Amount (in Rs.): 5206.0858411101
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 3707.61 Rs. 3707.61
2 Contingency @ Rs. 2000 Rs. 2000
Total Addition Component Amount (in Rs.): 5707.61
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 2000 Rs. 2000
2 Royalty @ Rs. 4527.0311661827 Rs. 4527.0311661827
3 EMF @ Rs. 226.35155830913 Rs. 226.35155830913
4 DMF @ Rs. 452.70311661827 Rs. 452.70311661827
5 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 639.09 Rs. 639.09
6 Labour Cess @ Rs. 2000 Rs. 2000
Total Deduction Component Amount (in Rs.): 9845.1758411101
Total Net Amount (in Rs.): 190153.8262612