Final Dpr

State: Odisha District: Mayurbhanj Block: Kaptipada Gram Panchayat: Notto
Work Code: OD/365/3497/120207/391258/00033020 (Maintenance of CC Road from Nanasahi village road in PC PUR (CR-Q/22/24-25))
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Kaptipada Bill Status: Final Bill
Proposal Date: - Date of Commencement: 24-07-2025
Date of Completion: 06-08-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Repair and Maintenance Name of Executant: Madhusudan Das
Administrative Approval Details
Approval No.: OD/365/3497/120207/391258/00033020/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3497/120207/391258/00033020/TS
Fund Sanction No.: 6908
Fund Sanction Amount (in Rs.): 500000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 29.68 216.86588853924 6436.5795718446
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 22.545 8264.7501191 186328.79143511
3 Earth Work (AR0101a1) : Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. Cum 14.2464 163.317 2326.6793088
4 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 28.23 1083.016132 30573.54540636
5 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 36.71 240.77592 8838.8840232
6 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 38.54 6664.5787583 256852.86534488
Total Amount (in Rs.): 491357.3450902
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Semi-Skilled Skilled Un-Skilled
Rs. 512 Rs. 562 Rs. 462
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 29.68 Square Meter - - 0.05 1.484 0.05 1.484
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 22.545 Cubic Meter 4.6 103.707 - - 0.68 15.3306
3 Earth Work (AR0101a1) : Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 14.2464 Cubic Meter 0.35 4.98624 - - - -
4 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 28.23 Cubic Meter 0.1236 3.489228 - - - -
5 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.71 Cubic Meter 0.516 18.94236 - - - -
6 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 38.54 Cubic Meter 3.9 150.306 - - 0.18 6.9372
Total Qty 1.484 23.7518 281.430828
Rate Per Man Day 512 562 462
Total Amount 759.808 13348.5116 130021.042536
Total Labour Amount (in Rs.): 144129.362136
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM104 BRM092 BRM340 BRM028 BRM056 BRM029 BRM044
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 29.68 Sqm 0.00267 0.0792456 0.126 3.73968 - - - - - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 22.545 Cum - - - - 3.23 72.82035 0.45 10.14525 0.9 20.2905 - - - -
3 Earth Work (AR0101a1) :.Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 14.2464 Cum - - - - - - - - - - - - - -
4 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 28.23 Cum - - - - - - - - - - 1 28.23 - -
5 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.71 Cum - - - - - - - - - - - - - -
6 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 38.54 Cum - - - - 2.29 88.2566 0.48 18.4992 - - - - 0.96 36.9984
Total Qty 0.0792456 3.73968 161.07695 28.64445 20.2905 28.23 36.9984
Rate Per Unit 58763.326 419.346 668.567 668.36 2193.43 661.94 1792.06
Total Amount 4656.7350268656 1568.21984928 107690.73323065 19144.804602 44505.791415 18686.5662 66303.352704
Total Material Amount (in Rs.): 262556.2030278
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM104 BRM092 BRM340 BRM028 BRM056 BRM029 BRM044
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 29.68 Sqm 0.00267 0.0792456 0.000614 0.01822352 - - - - - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 22.545 Cum - - - - 3.23 72.82035 0.45 10.14525 0.9 20.2905 - - - -
3 Earth Work (AR0101a1) :.Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 14.2464 Cum - - - - - - - - - - - - - -
4 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 28.23 Cum - - - - - - - - - - 1 28.23 - -
5 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.71 Cum - - - - - - - - - - - - - -
6 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 38.54 Cum - - - - 2.29 88.2566 0.48 18.4992 - - - - 0.96 36.9984
Total Qty 0.0792456 0.01822352 161.07695 28.64445 20.2905 28.23 36.9984
Rate Per Unit 0 0 0 353.25 579.5 353.25 579.5
Total Amount 0 0 0 10118.6519625 11758.34475 9972.2475 21440.5728
Total Royalty Amount (in Rs.): 53289.8170125
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 3641 Rs. 3641
2 Contingency @ Rs. 5000 Rs. 5000
Total Addition Component Amount (in Rs.): 8641
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 5000 Rs. 5000
2 Royalty @ Rs. 9438.16275 Rs. 9438.16275
3 Additional Royalty @ Rs. 42435.92985 Rs. 42435.92985
4 EMF @ Rs. 471.9081375 Rs. 471.9081375
5 DMF @ Rs. 943.816275 Rs. 943.816275
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 177 x 3.945) @ 1274.235 Rs. 1274.235
7 Labour Cess @ 1% Rs. 4999.983450902
Total Deduction Component Amount (in Rs.): 64564.035463402
Total Net Amount (in Rs.): 435434.30962679