Final Dpr

State: Odisha District: Balasore Block: Bhograi Gram Panchayat: Kumbhirgadi
Work Code: OD/346/3302/275558/391750/00034053 (Maintenance Of Adangapantai Pry School At Village Adangapantei.)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Bhograi Bill Status: Final Bill
Proposal Date: - Date of Commencement: 06-12-2025
Date of Completion: 09-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Primary School Building Project Sub-Category: Elementary School
Project Type: Repair and Maintenance Name of Executant: SOMANATH MALIK
Administrative Approval Details
Approval No.: OD/346/3302/275558/391750/00034053/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3302/275558/391750/00034053/TS
Fund Sanction No.: 13739
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 R.C.C. Work (AR0404B) : Reinforced cement concrete work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips.(Nominal mix as per IS-456, Table-9). - R.C.C. work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge(Nominal mix as per IS-456, Table-9). Cum 9.7315481198592 7390.007826724 71916.216771901
2 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. Qntl 9.94 8434.2122924 83836.070186456
3 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height Sqm 48.9982313584 663.90898015022 32530.36581032
4 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm Sqm 9.112297852 1048.4253517895 9553.5640810938
Total Amount (in Rs.): 197836.21684977
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 512 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404B) : Reinforced cement concrete work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips.(Nominal mix as per IS-456, Table-9). - R.C.C. work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge(Nominal mix as per IS-456, Table-9). 9.7315481198592 Cubic Meter 1.3333 12.975073108208 0.0573 0.55761770726793 0.1 0.97315481198592 - -
2 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 9.94 Quintal 0.8 7.952 0.044 0.43736 - - 0.3 2.982
3 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 48.9982313584 Square Meter - - 0.30555555555556 14.971681803956 0.30555555555556 14.971681803956 - -
4 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 9.112297852 Square Meter - - 0.6547619047619 5.9663854983333 0.6547619047619 5.9663854983333 - -
Total Qty 20.927073108208 21.911222114275 21.933045009557 2.982
Rate Per Man Day 462 562 512 612
Total Amount 9668.3077759922 12314.106828222 11229.719044893 1824.984
Total Labour Amount (in Rs.): 35037.117649108
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM060 BRM052 BRM340 BRM028 BRM162 BRM341 BRM084 BRM104
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404B) :.Reinforced cement concrete work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips.(Nominal mix as per IS-456, Table-9). - R.C.C. work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge(Nominal mix as per IS-456, Table-9). 9.7315481198592 Cum 0.36 3.5033573231493 0.54 5.255035984724 3.4733 33.800586084707 0.45 4.3791966539366 - - - - - - - -
2 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 9.94 Qntl - - - - - - - - 0.8 7.952 1.05 10.437 - - - -
3 R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 48.9982313584 Sqm - - - - - - - - - - - - 0.62222222222222 30.487788400782 0.0050222222222222 0.24608000637774
4 R.C.C. Work (AR0410d) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 9.112297852 Sqm - - - - - - - - - - - - 0.55238095238095 5.0334597658667 0.0051904761904762 0.047297165041333
Total Qty 3.5033573231493 5.255035984724 33.800586084707 4.3791966539366 7.952 10.437 35.521248166649 0.29337717141908
Rate Per Unit 3246.58 3210.2 567.932 984.79 90 6222.687 345.286 58668.206
Total Amount 11373.92981819 16869.716518161 19196.43445626 4312.5890728303 715.68 64946.184219 12264.98969447 17211.912328512
Total Material Amount (in Rs.): 146891.43610742
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM060 BRM052 BRM340 BRM028 BRM341 BRM084 BRM104
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404B) :.Reinforced cement concrete work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips.(Nominal mix as per IS-456, Table-9). - R.C.C. work of M-20 grade with 20mm & downgrade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge(Nominal mix as per IS-456, Table-9). 9.7315481198592 Cum 0.36 3.5033573231493 0.54 5.255035984724 3.4733 33.800586084707 0.45 4.3791966539366 - - - - - -
2 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 9.94 Qntl - - - - - - - - 1.05 10.437 - - - -
3 R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 48.9982313584 Sqm - - - - - - - - - - 0.0076666666666667 0.37565310708107 0.0050222222222222 0.24608000637774
4 R.C.C. Work (AR0410d) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 9.112297852 Sqm - - - - - - - - - - 0.0056666666666667 0.051636354494667 0.0051904761904762 0.047297165041333
Total Qty 3.5033573231493 5.255035984724 33.800586084707 4.3791966539366 10.437 0.42728946157573 0.29337717141908
Rate Per Unit 522.5 522.5 0 265.25 0 0 0
Total Amount 1830.5042013455 2745.7563020183 0 1161.5819124567 0 0 0
Total Royalty Amount (in Rs.): 5737.8424158205
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 1163 Rs. 1163
2 Contingency @ Rs. 1000 Rs. 1000
Total Addition Component Amount (in Rs.): 2163
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 1000 Rs. 1000
2 Royalty @ Rs. 1291.8630129113 Rs. 1291.8630129113
3 Additional Royalty @ Rs. 4252.1999509725 Rs. 4252.1999509725
4 EMF @ Rs. 64.593150645565 Rs. 64.593150645565
5 DMF @ Rs. 129.18630129113 Rs. 129.18630129113
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 268.26 Rs. 268.26
7 Labour Cess @ Rs. 2000 Rs. 2000
Total Deduction Component Amount (in Rs.): 9006.1024158205
Total Net Amount (in Rs.): 190993.11443395