Final Dpr

State: Odisha District: Nayagarh Block: Dasapalla Gram Panchayat: Similisahi
Work Code: OD/367/3524/120623/405563/00046415 (Improvement Of Road From Kuanria Canal To Bijayanagar)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Dasapalla Bill Status: Final Bill
Proposal Date: - Date of Commencement: 31-10-2025
Date of Completion: 22-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: Rasmi Ranjan Dash
Administrative Approval Details
Approval No.: OD/367/3524/120623/405563/00046415/AS
Technical Sanction Details
Technical Sanction No.: OD/367/3524/120623/405563/00046415/TS
Fund Sanction No.: 15217
Fund Sanction Amount (in Rs.): 350000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 29.2968 701.882532 20562.912163498
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 29.2968 5353.81701728 156849.70639185
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 23.411736 6912.28520336 161828.59633777
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 27.6692 216.23489289764 5983.0464985634
Total Amount (in Rs.): 345224.26139168
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 29.2968 Cubic Meter 0.1236 3.62108448 - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 29.2968 Cubic Meter 3.9 114.25752 - - 0.18 5.273424
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 23.411736 Cubic Meter 4.6 107.6939856 - - 0.68 15.91998048
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 27.6692 Square Meter - - 0.05 1.38346 0.05 1.38346
Total Qty 225.57259008 22.57686448 1.38346
Rate Per Man Day 462 562 512
Total Amount 104214.53661696 12688.19783776 708.33152
Total Labour Amount (in Rs.): 117611.06597472
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 29.2968 Cum 1 29.2968 - - - - - - - - - - - -
2 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 29.2968 Cum - - 2.29 67.089672 0.48 14.062464 0.96 28.124928 - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 23.411736 Cum - - 3.23 75.61990728 0.45 10.5352812 - - 0.9 21.0705624 - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 27.6692 Sqm - - - - - - - - - - 0.00267 0.073876764 0.126 3.4863192
Total Qty 29.2968 142.70957928 24.5977452 28.124928 21.0705624 0.073876764 3.4863192
Rate Per Unit 332.58 593.572 469.21 1295.11 1737.73 58573.086 229.106
Total Amount 9743.529744 84708.410392388 11541.508025292 36424.87550208 36614.948399352 4327.1900511737 798.7366466352
Total Material Amount (in Rs.): 184159.19876092
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 29.2968 Cum 1 29.2968 - - - - - - - - - - - -
2 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 29.2968 Cum - - 2.29 67.089672 0.48 14.062464 0.96 28.124928 - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 23.411736 Cum - - 3.23 75.61990728 0.45 10.5352812 - - 0.9 21.0705624 - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 27.6692 Sqm - - - - - - - - - - 0.00267 0.073876764 0.000614 0.0169888888
Total Qty 29.2968 142.70957928 24.5977452 28.124928 21.0705624 0.073876764 0.0169888888
Rate Per Unit 305.25 0 305.25 199.5 199.5 0 0
Total Amount 8942.8482 0 7508.4617223 5610.923136 4203.5771988 0 0
Total Royalty Amount (in Rs.): 26265.8102571
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 980 Rs. 980
2 Contingency @ 1% Rs. 3452.2426139168
Total Addition Component Amount (in Rs.): 4432.2426139168
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ 1% Rs. 3496.565040056
2 Royalty @ Rs. 8281.722834 Rs. 8281.722834
3 Additional Royalty @ Rs. 16741.828998 Rs. 16741.828998
4 EMF @ Rs. 414.0861417 Rs. 414.0861417
5 DMF @ Rs. 828.1722834 Rs. 828.1722834
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 1132.215 Rs. 1132.215
7 Labour Cess @ 1% Rs. 3496.565040056
Total Deduction Component Amount (in Rs.): 34391.155337212
Total Net Amount (in Rs.): 315265.34866839