| State: Odisha |
District: Kendujhar |
Block: Ghatgaon |
Gram Panchayat: Mukundapurpatna |
Work Code: OD/361/3447/119344/386680/00049480 (CONST OF CC ROD AT MUNDA SAHI , MUKUNDAPURPATNA GP)
Project Category: Road
| Financial Year: 2025-26 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Ghatgaon |
Bill Status:
Final Bill
|
| Proposal Date: - |
Date of Commencement: 30-10-2025 |
| Date of Completion: 07-01-2026 |
Scheme Name: 5th SFC Grant in Aid |
| Scheme Component Name: Maintenance and improvement of Road infrastructure |
Project Sub-Category: CC Road |
| Project Type: New Work |
Name of Executant: SINGHU MURMU |
Administrative Approval Details
Approval No.: OD/361/3447/119344/386680/00049480/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3447/119344/386680/00049480/TS
Fund Sanction No.: 29133
Fund Sanction Amount (in Rs.): 230000
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge.
|
Cum |
14.48 |
609.851332 |
8830.64728736 |
| 2 |
Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge.
|
Cum |
17.63 |
5636.13246574 |
99365.015370996 |
| 3 |
Concrete (AR0307) : Fifth Floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
Cum |
11.1975 |
10017.278773607 |
112168.47906746 |
| 4 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
Sqm |
21.0365 |
216.52089686004 |
4554.8418467962 |
| 5 |
Earth Work (AR0114) : Filling of foundation with escalated earth - Filling in foundation and plinth with excavated materials in ordinary soil including watering and ramming as directed by the Engineer-in-charge.
|
Cum |
2.4 |
99.54497784 |
238.907946816 |
| 6 |
Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface.
|
Sqm |
149.3 |
4.6662 |
696.66366 |
| 7 |
Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge
|
Cum |
3.6 |
240.77592 |
866.793312 |
Total Amount (in Rs.): 226721.34849143
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Un-Skilled
|
Skilled
|
Semi-Skilled
|
| Rs. 462 |
Rs. 562 |
Rs. 512 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge.
|
14.48 |
Cubic Meter |
0.1236 |
1.789728 |
- |
- |
- |
- |
| 2 |
Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge.
|
17.63 |
Cubic Meter |
3.9 |
68.757 |
- |
- |
0.18 |
3.1734 |
| 3 |
Concrete (AR0307) : Fifth Floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
11.1975 |
Cubic Meter |
9.2522430625 |
103.60199169234 |
- |
- |
1.3677228875 |
15.315077032781 |
| 4 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
21.0365 |
Square Meter |
- |
- |
0.05 |
1.051825 |
0.05 |
1.051825 |
| 5 |
Earth Work (AR0114) : Filling of foundation with escalated earth - Filling in foundation and plinth with excavated materials in ordinary soil including watering and ramming as directed by the Engineer-in-charge.
|
2.4 |
Cubic Meter |
0.213332 |
0.5119968 |
- |
- |
- |
- |
| 6 |
Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface.
|
149.3 |
Square Meter |
0.01 |
1.493 |
- |
- |
- |
- |
| 7 |
Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge
|
3.6 |
Cubic Meter |
0.516 |
1.8576 |
- |
- |
- |
- |
| Total Qty |
178.01131649234 |
19.540302032781 |
1.051825 |
| Rate Per Man Day |
462 |
562 |
512 |
| Total Amount |
82241.228219463 |
10981.649742423 |
538.5344 |
Total Labour Amount (in Rs.): 93761.412361886
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM029 |
BRM340 |
BRM028 |
BRM045 |
BRM056 |
BRM104 |
BRM092 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. |
14.48 |
Cum |
1 |
14.48 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
17.63 |
Cum |
- |
- |
2.29 |
40.3727 |
0.48 |
8.4624 |
0.96 |
16.9248 |
- |
- |
- |
- |
- |
- |
| 3 |
Concrete (AR0307) :.Fifth Floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
11.1975 |
Cum |
- |
- |
3.23 |
36.167925 |
0.45 |
5.038875 |
- |
- |
0.9 |
10.07775 |
- |
- |
- |
- |
| 4 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
21.0365 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.00267 |
0.056167455 |
0.126 |
2.650599 |
| 5 |
Earth Work (AR0114) :.Filling of foundation with escalated earth - Filling in foundation and plinth with excavated materials in ordinary soil including watering and ramming as directed by the Engineer-in-charge. |
2.4 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 6 |
Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. |
149.3 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 7 |
Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge |
3.6 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
14.48 |
76.540625 |
13.501275 |
16.9248 |
10.07775 |
0.056167455 |
2.650599 |
| Rate Per Unit |
461.21 |
592.307 |
1018.91 |
1221.31 |
1971.51 |
58668.206 |
276.666 |
| Total Amount |
6678.3208 |
45335.547971875 |
13756.58411025 |
20670.427488 |
19868.3849025 |
3295.2438204357 |
733.330622934 |
Total Material Amount (in Rs.): 110337.83971599
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM029 |
BRM340 |
BRM028 |
BRM045 |
BRM056 |
BRM104 |
BRM092 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. |
14.48 |
Cum |
1 |
14.48 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
17.63 |
Cum |
- |
- |
2.29 |
40.3727 |
0.48 |
8.4624 |
0.96 |
16.9248 |
- |
- |
- |
- |
- |
- |
| 3 |
Concrete (AR0307) :.Fifth Floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
11.1975 |
Cum |
- |
- |
3.23 |
36.167925 |
0.45 |
5.038875 |
- |
- |
0.9 |
10.07775 |
- |
- |
- |
- |
| 4 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
21.0365 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.00267 |
0.056167455 |
0.000614 |
0.012916411 |
| 5 |
Earth Work (AR0114) :.Filling of foundation with escalated earth - Filling in foundation and plinth with excavated materials in ordinary soil including watering and ramming as directed by the Engineer-in-charge. |
2.4 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 6 |
Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. |
149.3 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 7 |
Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge |
3.6 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
14.48 |
76.540625 |
13.501275 |
16.9248 |
10.07775 |
0.056167455 |
0.012916411 |
| Rate Per Unit |
85.5 |
0 |
230.5 |
328 |
328 |
0 |
0 |
| Total Amount |
1238.04 |
0 |
3112.0438875 |
5551.3344 |
3305.502 |
0 |
0 |
Total Royalty Amount (in Rs.): 13206.9202875
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Display Citizen Board @
Rs. 1011
|
Rs. 1011 |
| 2 |
Contingency @
1%
|
Rs. 2267 |
Total Addition Component Amount (in Rs.): 3278
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| 1 |
Contingency @
1%
|
Rs. 2300 |
| 2 |
Royalty @
Rs. 4489.676125
|
Rs. 4490 |
| 3 |
Additional Royalty @
Rs. 8043.79274375
|
Rs. 8044 |
| 4 |
EMF @
Rs. 224.48380625
|
Rs. 224 |
| 5 |
DMF @
Rs. 448.9676125
|
Rs. 449 |
| 6 |
Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 607.53
|
Rs. 607.53 |
| 7 |
Labour Cess @
1%
|
Rs. 2300 |
Total Deduction Component Amount (in Rs.): 18414.53
Total Net Amount (in Rs.): 211584.81849143