Final Dpr

State: Odisha District: Puri Block: Nimapada Gram Panchayat: Sainsasasan
Work Code: OD/369/3543/121033/408957/00049752 (CONST OF CC ROAD FROM TORIHABANDHA RD ROAD PRADHAN SAHI CLUB HOUSE TO DANDAMUNDA SAHI ROAD)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Nimapada Bill Status: Final Bill
Proposal Date: 10-12-2024 Date of Commencement: 13-09-2025
Date of Completion: 19-10-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: CC Road
Project Type: New Work Name of Executant: ANURAKTA DASH
Administrative Approval Details
Approval No.: OD/369/3543/121033/408957/00049752/AS
Technical Sanction Details
Technical Sanction No.: OD/369/3543/121033/408957/00049752/TS
Fund Sanction No.: 29143
Fund Sanction Amount (in Rs.): 143788
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. Sqm 105.90942 4.6662 494.194535604
2 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 2.4210864 240.77592 582.93930535949
3 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 9.829610784 591.903632 5818.182324196
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 12.250697184 6122.5837915 75005.920013333
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 7.4756352 7663.0583145 57286.228475529
6 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 19.27551444 216.23489289764 4168.0388004803
Total Amount (in Rs.): 143355.5034545
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. 105.90942 Square Meter 0.01 1.0590942 - - - -
2 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.4210864 Cubic Meter 0.516 1.2492805824 - - - -
3 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.829610784 Cubic Meter 0.1236 1.2149398929024 - - - -
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 12.250697184 Cubic Meter 3.9 47.7777190176 - - 0.18 2.20512549312
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 7.4756352 Cubic Meter 4.6 34.38792192 - - 0.68 5.083431936
6 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.27551444 Square Meter - - 0.05 0.963775722 0.05 0.963775722
Total Qty 85.688955612902 8.25233315112 0.963775722
Rate Per Man Day 462 562 512
Total Amount 39588.297493161 4637.8112309294 493.453169664
Total Labour Amount (in Rs.): 44719.561893754
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. 105.90942 Sqm - - - - - - - - - - - - - -
2 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.4210864 Cum - - - - - - - - - - - - - -
3 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.829610784 Cum 1 9.829610784 - - - - - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 12.250697184 Cum - - 2.29 28.05409655136 0.48 5.88033464832 0.96 11.76066929664 - - - - - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 7.4756352 Cum - - 3.23 24.146301696 0.45 3.36403584 - - 0.9 6.72807168 - - - -
6 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.27551444 Sqm - - - - - - - - - - 0.00267 0.0514656235548 0.126 2.42871481944
Total Qty 9.829610784 52.20039824736 9.24437048832 11.76066929664 6.72807168 0.0514656235548 2.42871481944
Rate Per Unit 453.69 589.887 468.19 1966.51 2378.13 58573.086 229.106
Total Amount 4459.596116593 30792.33632094 4328.1218189265 23127.473778536 16000.229104358 3014.5003945189 556.43313742262
Total Material Amount (in Rs.): 82278.690671295
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. 105.90942 Sqm - - - - - - - - - - - - - -
2 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.4210864 Cum - - - - - - - - - - - - - -
3 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.829610784 Cum 1 9.829610784 - - - - - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 12.250697184 Cum - - 2.29 28.05409655136 0.48 5.88033464832 0.96 11.76066929664 - - - - - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 7.4756352 Cum - - 3.23 24.146301696 0.45 3.36403584 - - 0.9 6.72807168 - - - -
6 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.27551444 Sqm - - - - - - - - - - 0.00267 0.0514656235548 0.000614 0.01183516586616
Total Qty 9.829610784 52.20039824736 9.24437048832 11.76066929664 6.72807168 0.0514656235548 0.01183516586616
Rate Per Unit 75.25 0 75.25 309.5 309.5 0 0
Total Amount 739.678211496 0 695.63887924608 3639.9271473101 2082.33818496 0 0
Total Royalty Amount (in Rs.): 7157.5824230122
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 200 Rs. 200
2 Contingency @ Rs. 232.45 Rs. 232.45
Total Addition Component Amount (in Rs.): 432.45
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 232.45 Rs. 232.45
2 Royalty @ Rs. 3071.1256714944 Rs. 3071.1256714944
3 Additional Royalty @ Rs. 3625.7879007936 Rs. 3625.7879007936
4 EMF @ Rs. 153.55628357472 Rs. 153.55628357472
5 DMF @ Rs. 307.11256714944 Rs. 307.11256714944
6 Labour Cess @ Rs. 1438 Rs. 1438
7 Any Other Lumpsum Bill @ Rs. 416 Rs. 416
Total Deduction Component Amount (in Rs.): 9244.0324230122
Total Net Amount (in Rs.): 134543.92103149