Final Dpr

State: Odisha District: Khordha Block: Balianta Gram Panchayat: Jhinti Sasan
Work Code: OD/362/3456/119542/407665/00061573 (CONSTRUCTION OF KALYAN MANDAP AT HATAPOKHARISAHI ,JHINTISASAN GP)
Project Category: Building
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Balianta Bill Status: Final Bill
Proposal Date: 02-05-2025 Date of Commencement: 06-11-2025
Date of Completion: 24-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Creation of Capital Asset for Revenue Generation Project Sub-Category: Kalyan Mandap
Project Type: New Work Name of Executant: RANJIT BALABANTARAY
Administrative Approval Details
Approval No.: OD/362/3456/119542/407665/00061573/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3456/119542/407665/00061573/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 1000000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) Cum 43.317475 6172.280204695 267367.59345987
2 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. Qntl 50.144894 9008.7358242 451742.10297851
3 R.C.C. Work (AR0410e) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm Sqm 15 499.15267251462 7487.2900877193
4 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm Sqm 124.429 1047.3822930467 130324.73134151
5 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height Sqm 200.115 662.689943368 132614.19801709
Total Amount (in Rs.): 989535.9158847
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 512 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 43.317475 Cubic Meter 1.3333 57.7551894175 0.0573 2.4820913175 0.1 4.3317475 - -
2 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 50.144894 Quintal 0.8 40.1159152 0.044 2.206375336 - - 0.3 15.0434682
3 R.C.C. Work (AR0410e) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 15 Square Meter - - 0.16025641025641 2.4038461538462 0.16025641025641 2.4038461538462 - -
4 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 124.429 Square Meter - - 0.6547619047619 81.471369047619 0.6547619047619 81.471369047619 - -
5 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 200.115 Square Meter - - 0.30555555555556 61.14625 0.30555555555556 61.14625 - -
Total Qty 97.8711046175 149.35321270147 149.70993185497 15.0434682
Rate Per Man Day 462 562 512 612
Total Amount 45216.450333285 83936.505538223 76651.485109742 9206.6025384
Total Labour Amount (in Rs.): 215011.04351965
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM060 BRM052 BRM162 BRM341 BRM094 BRM104 BRM084
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404A) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 43.317475 Cum 3.4733 150.4545859175 0.45 19.49286375 0.36 15.594291 0.54 23.3914365 - - - - - - - - - -
2 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 50.144894 Qntl - - - - - - - - 0.8 40.1159152 1.05 52.6521387 - - - - - -
3 R.C.C. Work (AR0410e) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 15 Sqm - - - - - - - - - - - - 0.26923076923077 4.0384615384615 0.0052948717948718 0.079423076923077 - -
4 R.C.C. Work (AR0410d) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 124.429 Sqm - - - - - - - - - - - - - - 0.0051904761904762 0.64584576190476 0.55238095238095 68.73220952381
5 R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 200.115 Sqm - - - - - - - - - - - - - - 0.0050222222222222 1.005022 0.62222222222222 124.516
Total Qty 150.4545859175 19.49286375 15.594291 23.3914365 40.1159152 52.6521387 4.0384615384615 1.7302908388278 193.24820952381
Rate Per Unit 569.387 481.81 2397.58 2382.2 90.1 6679.917 240.106 58573.086 250.166
Total Amount 85666.885311808 9391.8566833875 37388.56021578 55723.0800303 3614.44395952 351711.91638849 969.65884615385 101348.47410768 48344.131583733
Total Material Amount (in Rs.): 694159.00712685
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM060 BRM052 BRM341 BRM094 BRM104 BRM084
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404A) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 43.317475 Cum 3.4733 150.4545859175 0.45 19.49286375 0.36 15.594291 0.54 23.3914365 - - - - - - - -
2 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 50.144894 Qntl - - - - - - - - 1.05 52.6521387 - - - - - -
3 R.C.C. Work (AR0410e) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 15 Sqm - - - - - - - - - - 0.0035384615384615 0.053076923076923 0.0052948717948718 0.079423076923077 - -
4 R.C.C. Work (AR0410d) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 124.429 Sqm - - - - - - - - - - - - 0.0051904761904762 0.64584576190476 0.0056666666666667 0.70509766666667
5 R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 200.115 Sqm - - - - - - - - - - - - 0.0050222222222222 1.005022 0.0076666666666667 1.534215
Total Qty 150.4545859175 19.49286375 15.594291 23.3914365 52.6521387 0.053076923076923 1.7302908388278 2.2393126666667
Rate Per Unit 0 146.25 319.5 319.5 0 0 0 0
Total Amount 0 2850.8313234375 4982.3759745 7473.56396175 0 0 0 0
Total Royalty Amount (in Rs.): 15306.771259687
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 568 Rs. 568
2 Contingency @ 1% Rs. 9895.359158847
Total Addition Component Amount (in Rs.): 10463.359158847
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 9895.35 Rs. 9895.35
2 Royalty @ Rs. 5750.39480625 Rs. 5750.39480625
3 Additional Royalty @ Rs. 8693.8172325 Rs. 8693.8172325
4 EMF @ Rs. 287.5197403125 Rs. 287.5197403125
5 DMF @ Rs. 575.039480625 Rs. 575.039480625
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 1187.445 Rs. 1187.445
7 Labour Cess @ Rs. 9895.35 Rs. 9895.35
8 Any Other Lumpsum Bill @ Rs. 19790 Rs. 19790
Total Deduction Component Amount (in Rs.): 56074.916259688
Total Net Amount (in Rs.): 943924.35878386