Final Dpr

State: Odisha District: Mayurbhanj Block: Badasahi Gram Panchayat: Naupal
Work Code: OD/365/3487/120055/390598/00061915 (CONSTRUCTION OF CC ROAD FROM GALU NAIK HOUSE TO PADMA BATI BINDHANI HOUSE)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Badasahi Bill Status: Final Bill
Proposal Date: 14-02-2025 Date of Commencement: 24-10-2025
Date of Completion: 25-10-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: ASHOK KUMAR NAYAK
Administrative Approval Details
Approval No.: OD/365/3487/120055/390598/00061915/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3487/120055/390598/00061915/TS
Fund Sanction No.: 6908
Fund Sanction Amount (in Rs.): 186532
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 2.9032404 240.77592 699.03037829117
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 11.51097123 1602.277332 18443.768271133
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 13.32549648 6884.4233373 91738.358948021
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 19.1374 216.23489289764 4138.1736393393
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 7.94340608256 8457.8472721 67184.115466563
Total Amount (in Rs.): 182203.44670335
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.9032404 Cubic Meter 0.516 1.4980720464 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.51097123 Cubic Meter 0.1236 1.422756044028 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.32549648 Cubic Meter 3.9 51.969436272 - - 0.18 2.3985893664
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.1374 Square Meter - - 0.05 0.95687 0.05 0.95687
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 7.94340608256 Cubic Meter 4.6 36.539667979776 - - 0.68 5.4015161361408
Total Qty 91.429932342204 8.7569755025408 0.95687
Rate Per Man Day 462 562 512
Total Amount 42240.628742098 4921.4202324279 489.91744
Total Labour Amount (in Rs.): 47651.966414526
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM104 BRM092 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.9032404 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.51097123 Cum 1 11.51097123 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.32549648 Cum - - 2.29 30.5153869392 0.48 6.3962383104 0.96 12.7924766208 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.1374 Sqm - - - - - - - - 0.00267 0.051096858 0.126 2.4113124 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 7.94340608256 Cum - - 3.23 25.657201646669 0.45 3.574532737152 - - - - - - 0.9 7.149065474304
Total Qty 11.51097123 56.172588585869 9.970771047552 12.7924766208 0.051096858 2.4113124 7.149065474304
Rate Per Unit 740.06 656.677 746.48 1818.1 58573.086 229.106 2219.47
Total Amount 8518.8093684738 36887.246954803 7442.9811715766 23258.001744276 2992.9006579638 552.4461387144 15867.136348253
Total Material Amount (in Rs.): 95519.522384061
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM104 BRM092 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.9032404 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.51097123 Cum 1 11.51097123 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.32549648 Cum - - 2.29 30.5153869392 0.48 6.3962383104 0.96 12.7924766208 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.1374 Sqm - - - - - - - - 0.00267 0.051096858 0.000614 0.0117503636 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 7.94340608256 Cum - - 3.23 25.657201646669 0.45 3.574532737152 - - - - - - 0.9 7.149065474304
Total Qty 11.51097123 56.172588585869 9.970771047552 12.7924766208 0.051096858 0.0117503636 7.149065474304
Rate Per Unit 789.25 0 789.25 551.5 0 0 551.5
Total Amount 9085.0340432775 0 7869.4310492804 7055.0508563712 0 0 3942.7096090787
Total Royalty Amount (in Rs.): 27952.225558008
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 2000 Rs. 2000
2 Any Other Lumpsum @ Rs. 463.55 Rs. 463.55
3 Contingency @ Rs. 1864 Rs. 1864
Total Addition Component Amount (in Rs.): 4327.55
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 1865 Rs. 1865
2 Royalty @ Rs. 3344.2614520778 Rs. 3344.2614520778
3 Additional Royalty @ Rs. 24106.324888118 Rs. 24106.324888118
4 EMF @ Rs. 167.21307260389 Rs. 167.21307260389
5 DMF @ Rs. 334.42614520778 Rs. 334.42614520778
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 52 x 3.945) @ 449.73 Rs. 449.73
7 Labour Cess @ Rs. 1865 Rs. 1865
8 Any Other Lumpsum Bill @ Rs. 2236.05 Rs. 2236.05
Total Deduction Component Amount (in Rs.): 34368.005558007
Total Net Amount (in Rs.): 152162.99114534