Final Dpr

State: Odisha District: Jagatsinghpur Block: Erasama Gram Panchayat: Nuadihi
Work Code: OD/355/3388/118109/397331/00062267 (Repair and maintenance of PHC building at Mallipur)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Erasama Bill Status: 1st Bill
Proposal Date: - Date of Commencement: 20-11-2025
Date of Completion: - Scheme Name: Asset Management Health and Family Welfare Department
Scheme Component Name: Self/Personal Deposit Project Sub-Category: Primary Health Centre
Project Type: Repair and Maintenance Name of Executant: Susanta Kumar Nanda
Administrative Approval Details
Approval No.: OD/355/3388/118109/397331/00062267/AS
Technical Sanction Details
Technical Sanction No.: OD/355/3388/118109/397331/00062267/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 155000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. Sqm 28.6605755 230.34345832053 6601.7760781267
2 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. Sqm 155.0960121909 79.21834 12286.448626383
3 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) Sqm 140.47212309 160.71529806685 22576.019132493
4 Painting (AR0921b) : Finishing wall One Coat with distemper of approved shades with one coat water bound Primer on old work (Inside) - Finishing wall surface with One Coat with distemper of approved shades above one coat waterbound Primer on old work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge..(Inside) Sqm 376.6021081293 122.68977321371 46205.227238189
Total Amount (in Rs.): 87669.471075191
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Highly-Skilled Un-Skilled Skilled
Rs. 612 Rs. 462 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 28.6605755 Square Meter 0.17204301075269 4.9308516989247 - - 0.18817204301075 5.3931190456989
2 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 155.0960121909 Square Meter 0.057 8.8404726948813 0.05 7.754800609545 - -
3 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 140.47212309 Square Meter 0.11776344086022 16.542480560018 - - 0.10776344086022 15.137759329118
4 Painting (AR0921b) : Finishing wall One Coat with distemper of approved shades with one coat water bound Primer on old work (Inside) - Finishing wall surface with One Coat with distemper of approved shades above one coat waterbound Primer on old work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge..(Inside) 376.6021081293 Square Meter 0.093763440860215 35.311509493414 - - 0.086763440860215 32.675294736509
Total Qty 53.206173111326 65.625314447238 7.754800609545
Rate Per Man Day 612 462 562
Total Amount 32562.177944131 30318.895274624 4358.1979425643
Total Labour Amount (in Rs.): 67239.27116132
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM137 BRM141 BRMMR0038 BRM255 BRM253 BRM142
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 28.6605755 Sqm 0.054 1.547671077 0.125 3.5825719375 - - - - - - - -
2 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 155.0960121909 Sqm - - - - 0.8 124.07680975272 - - - - - -
3 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 140.47212309 Sqm - - - - - - 0.125 17.55901538625 0.090322580645161 12.687804666194 - -
4 Painting(AR0921b) :.Finishing wall One Coat with distemper of approved shades with one coat water bound Primer on old work (Inside) - Finishing wall surface with One Coat with distemper of approved shades above one coat waterbound Primer on old work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge..(Inside) 376.6021081293 Sqm - - - - - - - - 0.084 31.634577082861 0.166 62.515949949464
Total Qty 1.547671077 3.5825719375 124.07680975272 17.55901538625 44.322381749055 62.515949949464
Rate Per Unit 142.94787 205.58787 30 195.03787 159.27787 70.34787
Total Amount 221.23628391776 736.5333337524 3722.3042925816 3424.6729602314 7059.5745583163 4397.8639199714
Total Material Amount (in Rs.): 19562.185348771
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM137 BRM141 BRM255 BRM253 BRM142
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 28.6605755 Sqm 0.054 1.547671077 0.125 3.5825719375 - - - - - -
2 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 155.0960121909 Sqm - - - - - - - - - -
3 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 140.47212309 Sqm - - - - 0.125 17.55901538625 0.090322580645161 12.687804666194 - -
4 Painting(AR0921b) :.Finishing wall One Coat with distemper of approved shades with one coat water bound Primer on old work (Inside) - Finishing wall surface with One Coat with distemper of approved shades above one coat waterbound Primer on old work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge..(Inside) 376.6021081293 Sqm - - - - - - 0.084 31.634577082861 0.166 62.515949949464
Total Qty 1.547671077 3.5825719375 17.55901538625 44.322381749055 62.515949949464
Rate Per Unit 0 0 0 0 0
Total Amount 0 0 0 0 0
Total Royalty Amount (in Rs.): 0
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for PH Work @ Rs. 4600 Rs. 4600
2 Display Citizen Board @ Rs. 1000 Rs. 1000
3 Any Other Lumpsum @ Rs. 56000 Rs. 56000
4 Contingency @ Rs. 1550 Rs. 1550
Total Addition Component Amount (in Rs.): 63150
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 150819.47107519