Final Dpr

State: Odisha District: Nabarangpur Block: Tentulikhunti Gram Panchayat: Tentulikhunti
Work Code: OD/366/3521/120569/428000/00062804 (REPAIR AND MAINTENANCE OF CLASS ROOM AT GPS HATHIPAKHANA)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Tentulikhunti Bill Status: Final Bill
Proposal Date: 25-07-2025 Date of Commencement: 12-11-2025
Date of Completion: 13-11-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: Elementary School
Project Type: New Work Name of Executant: BRAJABIHARI MAHAKUD
Administrative Approval Details
Approval No.: OD/366/3521/120569/428000/00062804/AS
Technical Sanction Details
Technical Sanction No.: OD/366/3521/120569/428000/00062804/TS
Fund Sanction No.: 28365
Fund Sanction Amount (in Rs.): 100000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Plastering (AR1014k) : 16mm thick cement Plaster in CM (1:6) over brick work in inside (inside)(For repair and maintenance) . - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc. comp. and as per direction of Engineer-in-charge(For repair and maintenance). Sqm 147.516 246.063852366 36298.355245623
2 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. Sqm 301.689 71.83753306751 21672.593513604
3 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) Sqm 74.489 78.8505283 5873.4970025387
4 Painting (AR0918Ai) : Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. Sqm 138.738 57.09560199 7921.3296288886
5 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. Sqm 138.738 166.9033635096 23155.838846595
Total Amount (in Rs.): 94921.614237249
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Plastering (AR1014k) : 16mm thick cement Plaster in CM (1:6) over brick work in inside (inside)(For repair and maintenance) . - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc. comp. and as per direction of Engineer-in-charge(For repair and maintenance). 147.516 Square Meter 0.2448 36.1119168 0.1632 24.0746112 - -
2 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 301.689 Square Meter 0.053763440860215 16.219838709677 - - 0.053763440860215 16.219838709677
3 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 74.489 Square Meter 0.062 4.618318 - - 0.052 3.873428
4 Painting (AR0918Ai) : Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 138.738 Square Meter 0.043 5.965734 - - 0.036 4.994568
5 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 138.738 Square Meter 0.12 16.64856 0.14 19.42332 - -
Total Qty 79.564367509677 43.4979312 25.087834709677
Rate Per Man Day 462 562 612
Total Amount 36758.737789471 24445.8373344 15353.754842323
Total Labour Amount (in Rs.): 76558.329966194
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM253 BRM142 BRM255
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Plastering (AR1014k) :.16mm thick cement Plaster in CM (1:6) over brick work in inside (inside)(For repair and maintenance) . - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc. comp. and as per direction of Engineer-in-charge(For repair and maintenance). 147.516 Sqm 0.043 6.343188 0.018 2.655288 - - - - - -
2 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 301.689 Sqm - - - - 0.084 25.341876 - - - -
3 Painting(AR0922) :.Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 74.489 Sqm - - - - - - 0.25 18.62225 - -
4 Painting(AR0918Ai) :.Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 138.738 Sqm - - - - - - - - 0.075 10.40535
5 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 138.738 Sqm 0.0358 4.9668204 0.015 2.08107 - - - - - -
Total Qty 11.3100084 4.736358 25.341876 18.62225 10.40535
Rate Per Unit 585.117 482.34 159.33732 70.40732 195.09732
Total Amount 6617.6781849828 2284.53491772 4037.9066056123 1311.14271487 2030.055898662
Total Material Amount (in Rs.): 16281.318321847
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM253 BRM142 BRM255
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Plastering (AR1014k) :.16mm thick cement Plaster in CM (1:6) over brick work in inside (inside)(For repair and maintenance) . - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc. comp. and as per direction of Engineer-in-charge(For repair and maintenance). 147.516 Sqm 0.043 6.343188 0.018 2.655288 - - - - - -
2 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 301.689 Sqm - - - - 0.084 25.341876 - - - -
3 Painting(AR0922) :.Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 74.489 Sqm - - - - - - 0.25 18.62225 - -
4 Painting(AR0918Ai) :.Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 138.738 Sqm - - - - - - - - 0.075 10.40535
5 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 138.738 Sqm 0.0358 4.9668204 0.015 2.08107 - - - - - -
Total Qty 11.3100084 4.736358 25.341876 18.62225 10.40535
Rate Per Unit 0 40.25 0 0 0
Total Amount 0 190.6384095 0 0 0
Total Royalty Amount (in Rs.): 190.6384095
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 3500 Rs. 3500
2 Contingency @ Rs. 1000 Rs. 1000
Total Addition Component Amount (in Rs.): 4500
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 1000 Rs. 1000
2 Royalty @ Rs. 165.77253 Rs. 165.77253
3 EMF @ Rs. 8.2886265 Rs. 8.2886265
4 DMF @ Rs. 16.577253 Rs. 16.577253
5 Empty Gunny Bag (Cement x Gunny Bag Rate : 10 x 3.945) @ 90.735 Rs. 90.735
6 Labour Cess @ Rs. 1000 Rs. 1000
Total Deduction Component Amount (in Rs.): 2281.3734095
Total Net Amount (in Rs.): 97140.240827749