Final Dpr

State: Odisha District: Balangir Block: Belpara Gram Panchayat: Parlimal
Work Code: OD/345/3287/115838/420929/00063517 (CONSTRUCTION OF CEMENT OCNCRETE ROA AT MUNNAPALI UPPERPADA)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Belpara Bill Status: Final Bill
Proposal Date: 01-07-2023 Date of Commencement: 04-11-2025
Date of Completion: 12-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: JAGUNA NANDA SAMARTHA
Administrative Approval Details
Approval No.: OD/345/3287/115838/420929/00063517/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3287/115838/420929/00063517/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0101a) : Earthwork in ordinary soil within 50m, initial lead and 1.5m, initial lift - Earth work in ordinary soil within 50m, initial lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. Cum 9.255384 149.3184 1381.9991302656
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 30.316194 5287.45121715 160295.39686466
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 16.00884 6784.86799585 108617.86616668
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 48.9888 216.38948682983 10600.661292409
5 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 24.07887 605.613372 14582.48565465
Total Amount (in Rs.): 295478.40910866
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0101a) : Earthwork in ordinary soil within 50m, initial lead and 1.5m, initial lift - Earth work in ordinary soil within 50m, initial lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 9.255384 Cubic Meter 0.32 2.96172288 - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 30.316194 Cubic Meter 3.9 118.2331566 - - 0.18 5.45691492
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 16.00884 Cubic Meter 4.6 73.640664 - - 0.68 10.8860112
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 48.9888 Square Meter - - 0.05 2.44944 0.05 2.44944
5 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 24.07887 Cubic Meter 0.1236 2.976148332 - - - -
Total Qty 197.811691812 18.79236612 2.44944
Rate Per Man Day 462 562 512
Total Amount 91389.001617144 10561.30975944 1254.11328
Total Labour Amount (in Rs.): 103204.42465658
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM056 BRM104 BRM092 BRM029
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0101a) :.Earthwork in ordinary soil within 50m, initial lead and 1.5m, initial lift - Earth work in ordinary soil within 50m, initial lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 9.255384 Cum - - - - - - - - - - - - - -
2 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 30.316194 Cum 2.29 69.42408426 0.48 14.55177312 0.96 29.10354624 - - - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 16.00884 Cum 3.23 51.7085532 0.45 7.203978 - - 0.9 14.407956 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 48.9888 Sqm - - - - - - - - 0.00267 0.130800096 0.126 6.1725888 - -
5 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 24.07887 Cum - - - - - - - - - - - - 1 24.07887
Total Qty 121.13263746 21.75575112 29.10354624 14.407956 0.130800096 6.1725888 24.07887
Rate Per Unit 572.0931 492.204 1410.574 1811.944 58619.6948 275.7148 487.264
Total Amount 69299.146075668 10708.267724268 41052.705633942 26106.409426464 7667.4617073307 1701.8740864742 11732.76651168
Total Material Amount (in Rs.): 168268.63116583
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM056 BRM104 BRM092 BRM029
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0101a) :.Earthwork in ordinary soil within 50m, initial lead and 1.5m, initial lift - Earth work in ordinary soil within 50m, initial lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 9.255384 Cum - - - - - - - - - - - - - -
2 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 30.316194 Cum 2.29 69.42408426 0.48 14.55177312 0.96 29.10354624 - - - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 16.00884 Cum 3.23 51.7085532 0.45 7.203978 - - 0.9 14.407956 - - - - - -
4 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 48.9888 Sqm - - - - - - - - 0.00267 0.130800096 0.000614 0.0300791232 - -
5 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 24.07887 Cum - - - - - - - - - - - - 1 24.07887
Total Qty 121.13263746 21.75575112 29.10354624 14.407956 0.130800096 0.0300791232 24.07887
Rate Per Unit 0 55.25 189.5 189.5 0 0 55.25
Total Amount 0 1202.00524938 5515.12201248 2730.307662 0 0 1330.3575675
Total Royalty Amount (in Rs.): 10777.79249136
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 1400 Rs. 1400
2 Any Other Lumpsum @ Rs. 100 Rs. 100
3 Contingency @ 1% Rs. 2954.7840910866
Total Addition Component Amount (in Rs.): 4454.7840910866
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ 1% Rs. 2999.3319319975
2 Royalty @ Rs. 7260.7070304 Rs. 7260.7070304
3 Additional Royalty @ Rs. 2427.9794064 Rs. 2427.9794064
4 EMF @ Rs. 363.03535152 Rs. 363.03535152
5 DMF @ Rs. 726.07070304 Rs. 726.07070304
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 958.635 Rs. 958.635
7 Labour Cess @ 1% Rs. 2999.3319319975
8 Any Other Lumpsum Bill @ Rs. 100 Rs. 100
Total Deduction Component Amount (in Rs.): 17835.091355355
Total Net Amount (in Rs.): 282098.10184439