Final Dpr

State: Odisha District: Balangir Block: Turekela Gram Panchayat: Buromal
Work Code: OD/345/3297/116027/421208/00063610 (MAINTEANANCE OF ROAD FROM KUKUDAHAD JHANKARPADA TO PWD ROAD)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Turekela Bill Status: Final Bill
Proposal Date: - Date of Commencement: 06-11-2025
Date of Completion: 15-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES Project Sub-Category: CC Road
Project Type: Repair and Maintenance Name of Executant: TEJU PUTEL
Administrative Approval Details
Approval No.: OD/345/3297/116027/421208/00063610/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3297/116027/421208/00063610/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 500000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0122Ai) : Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. Cum 5.88706272 220.96043508 1300.8079399544
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 33.15330944 515.507232 17090.770781054
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 53.37433632 5144.64137936 274591.81922775
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 28.50227504 6651.11384432 189571.87611316
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 55.184382 216.23489289764 11932.788931392
Total Amount (in Rs.): 494488.06299331
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0122Ai) : Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 5.88706272 Cubic Meter 0.473534 2.7877243580525 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 33.15330944 Cubic Meter 0.1236 4.097749046784 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 53.37433632 Cubic Meter 3.9 208.159911648 - - 0.18 9.6073805376
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 28.50227504 Cubic Meter 4.6 131.110465184 - - 0.68 19.3815470272
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 55.184382 Square Meter - - 0.05 2.7592191 0.05 2.7592191
Total Qty 346.15585023684 31.7481466648 2.7592191
Rate Per Man Day 462 562 512
Total Amount 159924.00280942 17842.458425618 1412.7201792
Total Labour Amount (in Rs.): 179179.18141424
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0122Ai) :.Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 5.88706272 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 33.15330944 Cum 1 33.15330944 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 53.37433632 Cum - - 2.29 122.2272301728 0.48 25.6196814336 0.96 51.2393628672 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 28.50227504 Cum - - 3.23 92.0623483792 0.45 12.826023768 - - 0.9 25.652047536 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 55.184382 Sqm - - - - - - - - - - 0.00267 0.14734229994 0.126 6.953232132
Total Qty 33.15330944 214.289578552 38.4457052016 51.2393628672 25.652047536 0.14734229994 6.953232132
Rate Per Unit 413.05 572.212 417.99 1336.36 1737.73 58573.086 229.106
Total Amount 13693.974464192 122619.0683224 16069.920317217 68474.234961211 44576.332564733 8630.2932058234 1593.027200834
Total Material Amount (in Rs.): 275656.85103641
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0122Ai) :.Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 5.88706272 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 33.15330944 Cum 1 33.15330944 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 53.37433632 Cum - - 2.29 122.2272301728 0.48 25.6196814336 0.96 51.2393628672 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 28.50227504 Cum - - 3.23 92.0623483792 0.45 12.826023768 - - 0.9 25.652047536 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 55.184382 Sqm - - - - - - - - - - 0.00267 0.14734229994 0.000614 0.033883210548
Total Qty 33.15330944 214.289578552 38.4457052016 51.2393628672 25.652047536 0.14734229994 0.033883210548
Rate Per Unit 40.25 0 47.75 157 157 0 0
Total Amount 1334.42070496 0 1835.7824233764 8044.5799701504 4027.371463152 0 0
Total Royalty Amount (in Rs.): 15242.154561639
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 560 Rs. 560
2 Contingency @ Rs. 4951.5 Rs. 4951.5
Total Addition Component Amount (in Rs.): 5511.5
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 4951.5 Rs. 4951.5
2 Royalty @ Rs. 12501.848864872 Rs. 12501.848864872
3 Additional Royalty @ Rs. 865.028367036 Rs. 865.028367036
4 EMF @ Rs. 625.0924432436 Rs. 625.0924432436
5 DMF @ Rs. 1250.1848864872 Rs. 1250.1848864872
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 1696.35 Rs. 1696.35
7 Labour Cess @ 1% Rs. 4999.9956299331
8 Any Other Lumpsum Bill @ Rs. 1611 Rs. 1611
Total Deduction Component Amount (in Rs.): 28501.000191572
Total Net Amount (in Rs.): 471498.56280174