Final Dpr

State: Odisha District: Khordha Block: Chilika Gram Panchayat: Biribadi
Work Code: OD/362/3462/119639/408144/00064058 (Maintenance and Improvement of CC Road from RD Road to Biribadi High School East Side,Biribadi GP.)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Chilika Bill Status: Final Bill
Proposal Date: - Date of Commencement: 13-11-2025
Date of Completion: 15-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Repair and Maintenance Name of Executant: PRIYADARSHINI MADHUSMITA
Administrative Approval Details
Approval No.: OD/362/3462/119639/408144/00064058/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3462/119639/408144/00064058/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 19.46931211712 240.77592 4687.7415367667
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 16.749670368 1214.477732 20342.101680276
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 19.2563392608 216.23489289764 4163.8924576597
4 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 25.94092986624 5824.8348118 151101.63133534
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 15.21098076288 7457.4590886 113435.26673666
Total Amount (in Rs.): 293730.6337467
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled Skilled
Rs. 462 Rs. 512 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 19.46931211712 Cubic Meter 0.516 10.046165052434 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.749670368 Cubic Meter 0.1236 2.0702592574848 - - - -
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.2563392608 Square Meter - - 0.05 0.96281696304 0.05 0.96281696304
4 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.94092986624 Cubic Meter 3.9 101.16962647834 - - 0.18 4.6693673759232
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 15.21098076288 Cubic Meter 4.6 69.970511509248 - - 0.68 10.343466918758
Total Qty 183.2565622975 0.96281696304 15.975651257722
Rate Per Man Day 462 512 562
Total Amount 84664.531781446 492.96228507648 8978.3160068395
Total Labour Amount (in Rs.): 94135.810073362
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM104 BRM092 BRM340 BRM028 BRM045 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 19.46931211712 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.749670368 Cum 1 16.749670368 - - - - - - - - - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.2563392608 Sqm - - 0.00267 0.051414425826336 0.126 2.4262987468608 - - - - - - - -
4 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.94092986624 Cum - - - - - - 2.29 59.40472939369 0.48 12.451646335795 0.96 24.90329267159 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 15.21098076288 Cum - - - - - - 3.23 49.131467864102 0.45 6.844941343296 - - 0.9 13.689882686592
Total Qty 16.749670368 0.051414425826336 2.4262987468608 108.53619725779 19.296587679091 24.90329267159 13.689882686592
Rate Per Unit 1102.1 58573.086 229.106 572.954 1108.49 1649.27 2234.62
Total Amount 18459.811712573 3011.5015855666 555.87960069829 62186.248363641 21390.074476396 41072.253504474 30591.685649112
Total Material Amount (in Rs.): 177267.45489246
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM104 BRM092 BRM340 BRM028 BRM045 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 19.46931211712 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.749670368 Cum 1 16.749670368 - - - - - - - - - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.2563392608 Sqm - - 0.00267 0.051414425826336 0.000614 0.011823392306131 - - - - - - - -
4 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.94092986624 Cum - - - - - - 2.29 59.40472939369 0.48 12.451646335795 0.96 24.90329267159 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 15.21098076288 Cum - - - - - - 3.23 49.131467864102 0.45 6.844941343296 - - 0.9 13.689882686592
Total Qty 16.749670368 0.051414425826336 0.011823392306131 108.53619725779 19.296587679091 24.90329267159 13.689882686592
Rate Per Unit 43.25 0 0 0 43.25 199.5 199.5
Total Amount 724.423243416 0 0 0 834.57741712069 4968.2068879823 2731.1315959751
Total Royalty Amount (in Rs.): 9258.3391444941
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 770 Rs. 770
2 Any Other Lumpsum @ Rs. 2522.17 Rs. 2522.17
3 Contingency @ Rs. 2977 Rs. 2977
Total Addition Component Amount (in Rs.): 6269.17
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 2977 Rs. 2977
2 Royalty @ Rs. 6278.7318282119 Rs. 6278.7318282119
3 Additional Royalty @ Rs. 2037.7975420504 Rs. 2037.7975420504
4 EMF @ Rs. 313.9365914106 Rs. 313.9365914106
5 DMF @ Rs. 627.87318282119 Rs. 627.87318282119
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 99 x 3.945) @ 860.01 Rs. 860.01
7 Labour Cess @ Rs. 3000 Rs. 3000
8 Any Other Lumpsum Bill @ Rs. 6000 Rs. 6000
Total Deduction Component Amount (in Rs.): 22095.349144494
Total Net Amount (in Rs.): 277904.4546022