Final Dpr

State: Odisha District: Nayagarh Block: Odagaon Gram Panchayat: Godipalli
Work Code: OD/367/3529/120708/406738/00064216 (Construction Of Khamar Sahi CC Road)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Odagaon Bill Status: Final Bill
Proposal Date: - Date of Commencement: 13-11-2025
Date of Completion: 14-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: Sradhanjali Sathua Mohapatra
Administrative Approval Details
Approval No.: OD/367/3529/120708/406738/00064216/AS
Technical Sanction Details
Technical Sanction No.: OD/367/3529/120708/406738/00064216/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 3.76 240.77592 905.3174592
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 13.724 701.882532 9632.635869168
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 15.98 5352.13834678 85527.170781544
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 13.724 6904.20787986 94753.348943199
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 15.04 216.23489289764 3252.1727891805
Total Amount (in Rs.): 194070.64584229
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.76 Cubic Meter 0.516 1.94016 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.724 Cubic Meter 0.1236 1.6962864 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 15.98 Cubic Meter 3.9 62.322 - - 0.18 2.8764
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.724 Cubic Meter 4.6 63.1304 - - 0.68 9.33232
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 15.04 Square Meter - - 0.05 0.752 0.05 0.752
Total Qty 129.0888464 12.96072 0.752
Rate Per Man Day 462 562 512
Total Amount 59639.0470368 7283.92464 385.024
Total Labour Amount (in Rs.): 67307.9956768
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.76 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.724 Cum 1 13.724 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 15.98 Cum - - 2.29 36.5942 0.48 7.6704 0.96 15.3408 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.724 Cum - - 3.23 44.32852 0.45 6.1758 - - 0.9 12.3516 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 15.04 Sqm - - - - - - - - - - 0.00267 0.0401568 0.126 1.89504
Total Qty 13.724 80.92272 13.8462 15.3408 12.3516 0.0401568 1.89504
Rate Per Unit 332.58 587.627 534.31 1230.01 1672.63 58573.086 229.106
Total Amount 4564.32792 47552.37518544 7398.163122 18869.337408 20659.656708 2352.1076998848 434.16503424
Total Material Amount (in Rs.): 101830.13307756
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.76 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.724 Cum 1 13.724 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 15.98 Cum - - 2.29 36.5942 0.48 7.6704 0.96 15.3408 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.724 Cum - - 3.23 44.32852 0.45 6.1758 - - 0.9 12.3516 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 15.04 Sqm - - - - - - - - - - 0.00267 0.0401568 0.000614 0.00923456
Total Qty 13.724 80.92272 13.8462 15.3408 12.3516 0.0401568 0.00923456
Rate Per Unit 305.25 0 305.25 244.5 244.5 0 0
Total Amount 4189.251 0 4226.55255 3750.8256 3019.9662 0 0
Total Royalty Amount (in Rs.): 15186.59535
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 1500 Rs. 1500
2 Any Other Lumpsum @ Rs. 1441 Rs. 1441
3 Contingency @ Rs. 2000 Rs. 2000
Total Addition Component Amount (in Rs.): 4941
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 2000 Rs. 2000
2 Royalty @ Rs. 4564.969 Rs. 4564.969
3 Additional Royalty @ Rs. 9936.881 Rs. 9936.881
4 EMF @ Rs. 228.24845 Rs. 228.24845
5 DMF @ Rs. 456.4969 Rs. 456.4969
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 643.035 Rs. 643.035
7 Labour Cess @ Rs. 2000 Rs. 2000
Total Deduction Component Amount (in Rs.): 19829.63035
Total Net Amount (in Rs.): 179182.01549229