Final Dpr

State: Odisha District: Bargarh Block: Paikmal Gram Panchayat: Bhubaneswarpur
Work Code: OD/347/3320/116536/379718/00064539 (Maintenance of Market Complex at Bhubaneswarpur)
Project Category: Other Infrastructure
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Paikmal Bill Status: Final Bill
Proposal Date: - Date of Commencement: 04-12-2025
Date of Completion: 04-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Capital Assets Project Sub-Category: Rural Haat
Project Type: Repair and Maintenance Name of Executant: Purna Chandra Bariha
Administrative Approval Details
Approval No.: OD/347/3320/116536/379718/00064539/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3320/116536/379718/00064539/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 250000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 18.830672 240.77592 4533.9723750182
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 10.80002752 708.124332 7647.7622731816
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 14.225369600118 5578.35296346 79354.132665132
4 Plastering (AR1017) : 20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. Sqm 11.0090055 273.1441399856 3007.0453393942
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. Sqm 30.52699677 362.1955131092 11056.741258793
6 Roofing (AR1135i) : G.C.I. Sheet (0.40mm thick) in walling - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in walling including cost of nuts and bolts, fitting, labour and material etc. complete as per direction of Engineer-in-Charge. Sqm 41.620544 540.97316583945 22515.59745164
7 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 11.90438272 7142.13905002 85022.756690895
8 Iron Work (AR1703) : Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. Qntl 2.4546556 13248.912038252 32521.516128603
Total Amount (in Rs.): 245659.52418266
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 612 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 18.830672 Cubic Meter 0.516 9.716626752 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.80002752 Cubic Meter 0.1236 1.334883401472 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.225369600118 Cubic Meter 3.9 55.47894144046 - - 0.18 2.5605665280212 - -
4 Plastering (AR1017) : 20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 11.0090055 Square Meter 0.24 2.64216132 - - 0.16 1.76144088 - -
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 30.52699677 Square Meter 0.36 10.9897188372 - - - - 0.13 3.9685095801
6 Roofing (AR1135i) : G.C.I. Sheet (0.40mm thick) in walling - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in walling including cost of nuts and bolts, fitting, labour and material etc. complete as per direction of Engineer-in-Charge. 41.620544 Square Meter 0.21505376344086 8.9506546236559 - - - - 0.16129032258065 6.7129909677419
7 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.90438272 Cubic Meter 4.6 54.760160512 - - 0.68 8.0949802496 - -
8 Iron Work (AR1703) : Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 2.4546556 Quintal 4.9212598425197 12.079998031496 1.9685039370079 4.8319992125984 4.4291338582677 10.871998228346 - -
Total Qty 155.95314491828 23.288985885968 10.681500547842 4.8319992125984
Rate Per Man Day 462 562 612 512
Total Amount 72050.352952247 13088.410067914 6537.0783352793 2473.9835968504
Total Labour Amount (in Rs.): 94149.824952291
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM057 BRMMR0036 BRM150 BRM056 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 18.830672 Cum - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.80002752 Cum 1 10.80002752 - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.225369600118 Cum - - 2.29 32.57609638427 0.48 6.8281774080566 0.96 13.656354816113 - - - - - - - - - -
4 Plastering (AR1017) :.20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 11.0090055 Sqm - - 0.0744 0.8190700092 0.021 0.2311891155 - - - - - - - - - - - -
5 Flooring (AR0802ii) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 30.52699677 Sqm - - 0.0858 2.619216322866 0.012 0.36632396124 - - 0.023 0.70212092571 - - - - - - - -
6 Roofing (AR1135i) :.G.C.I. Sheet (0.40mm thick) in walling - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in walling including cost of nuts and bolts, fitting, labour and material etc. complete as per direction of Engineer-in-Charge. 41.620544 Sqm - - - - - - - - - - 0.10752688172043 4.475327311828 1 41.620544 - - - -
7 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.90438272 Cum - - 3.23 38.4511561856 0.45 5.356972224 - - - - - - - - 0.9 10.713944448 - -
8 Iron Work(AR1703) :.Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 2.4546556 Qntl - - - - - - - - - - - - - - - - 1 2.4546556
Total Qty 10.80002752 74.465538901936 12.782662708797 13.656354816113 0.70212092571 4.475327311828 41.620544 10.713944448 2.4546556
Rate Per Unit 466.51 642.957 474.14 1354.39 1458.93 30 334.3266733 1802.83 6234.642
Total Amount 5038.3208383552 47878.139495772 6060.7716967488 18496.030399396 1024.3452821461 134.25981935484 13914.858016456 19315.420469188 15303.898899295
Total Material Amount (in Rs.): 127166.04491671
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM057 BRM150 BRM056 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 18.830672 Cum - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.80002752 Cum 1 10.80002752 - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.225369600118 Cum - - 2.29 32.57609638427 0.48 6.8281774080566 0.96 13.656354816113 - - - - - - - -
4 Plastering (AR1017) :.20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 11.0090055 Sqm - - 0.0744 0.8190700092 0.021 0.2311891155 - - - - - - - - - -
5 Flooring (AR0802ii) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 30.52699677 Sqm - - 0.0858 2.619216322866 0.012 0.36632396124 - - 0.023 0.70212092571 - - - - - -
6 Roofing (AR1135i) :.G.C.I. Sheet (0.40mm thick) in walling - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in walling including cost of nuts and bolts, fitting, labour and material etc. complete as per direction of Engineer-in-Charge. 41.620544 Sqm - - - - - - - - - - 1 41.620544 - - - -
7 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.90438272 Cum - - 3.23 38.4511561856 0.45 5.356972224 - - - - - - 0.9 10.713944448 - -
8 Iron Work(AR1703) :.Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 2.4546556 Qntl - - - - - - - - - - - - - - 1 2.4546556
Total Qty 10.80002752 74.465538901936 12.782662708797 13.656354816113 0.70212092571 41.620544 10.713944448 2.4546556
Rate Per Unit 177.5 0 177.5 296.75 296.75 0 249.5 0
Total Amount 1917.0048848 0 2268.9226308114 4052.5232916816 208.35438470444 0 2673.129139776 0
Total Royalty Amount (in Rs.): 11119.934331773
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 4000 Rs. 4000
2 Contingency @ Rs. 340 Rs. 340
Total Addition Component Amount (in Rs.): 4340
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 340 Rs. 340
2 Royalty @ Rs. 4084.8087826849 Rs. 4084.8087826849
3 Additional Royalty @ Rs. 6356.7813219418 Rs. 6356.7813219418
4 EMF @ Rs. 204.24043913425 Rs. 204.24043913425
5 DMF @ Rs. 408.48087826849 Rs. 408.48087826849
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 595.695 Rs. 595.695
7 Labour Cess @ 1% Rs. 2499.9952418266
Total Deduction Component Amount (in Rs.): 14490.001663856
Total Net Amount (in Rs.): 235509.5225188