Final Dpr

State: Odisha District: Jajpur Block: Rasulpur Gram Panchayat: Brahmabarada
Work Code: OD/356/3402/118469/401372/00064757 (Improvement of Brahmabarada Degree College)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Rasulpur Bill Status: Final Bill
Proposal Date: - Date of Commencement: 02-12-2025
Date of Completion: 12-12-2025 Scheme Name: Chief Minister Special Assistant
Scheme Component Name: Chief Minister Special Assistance (CM-SA) Project Sub-Category: Secondary School
Project Type: Upgradation or Improvement Name of Executant: Bandana Tanty
Administrative Approval Details
Approval No.: OD/356/3402/118469/401372/00064757/AS
Technical Sanction Details
Technical Sanction No.: OD/356/3402/118469/401372/00064757/TS
Fund Sanction No.: 339
Fund Sanction Amount (in Rs.): 769125
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge Sqm 42.12 518.84606791032 21853.796380383
2 Other Building Items. (AR1911) : Stainless steel of 304 grade in hand railing using 50mm dia of 2mm - Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @ 0.90mtr. C/C and stainless square pipe bracing of size 32mm x 32mm x 2mm in 3 rows in staircase as per approved design and specification, buffing, polishing etc with cost,conveyance, taxes of all materials, labour,T&P etc. required for the complete in all respect. and as per direction of Engineer in Charge Rmt 40.2 3129.0244276074 125786.78198982
3 Flooring (AR0817al) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Granite Tiles Above 0.10 Sqm Above 0.10 Sqm & up to 0.4 sqm (10mm. thick) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Granite tiles including rubbing and polishing complete including cost of precast tiles. Sqm 101.255 2224.855728136 225277.76675241
4 Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. Cum 10.3295 4958.786040288 51221.780403155
5 Plastering (AR1014i) : 16mm thick cement Plaster in CM (1:6) over brick work in outside (outside) - 16mm thick cement Plaster in CM (1:6) over brick work in outside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. Sqm 471.51 244.341858522 115209.62971171
6 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. Sqm 73.776 189.0801132088 13949.574432092
7 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. Sqm 180.414 79.21834 14292.09759276
8 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) Sqm 1145.931 160.17640605073 183551.10916212
Total Amount (in Rs.): 751142.53642445
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Semi-Skilled Skilled
Rs. 462 Rs. 612 Rs. 512 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 42.12 Square Meter 0.21505376344086 9.058064516129 - - - - 0.16129032258065 6.7935483870968
2 Other Building Items. (AR1911) : Stainless steel of 304 grade in hand railing using 50mm dia of 2mm - Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @ 0.90mtr. C/C and stainless square pipe bracing of size 32mm x 32mm x 2mm in 3 rows in staircase as per approved design and specification, buffing, polishing etc with cost,conveyance, taxes of all materials, labour,T&P etc. required for the complete in all respect. and as per direction of Engineer in Charge 40.2 Meter - - 0.27300613496933 10.974846625767 - - 0.27300613496933 10.974846625767
3 Flooring (AR0817al) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Granite Tiles Above 0.10 Sqm Above 0.10 Sqm & up to 0.4 sqm (10mm. thick) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Granite tiles including rubbing and polishing complete including cost of precast tiles. 101.255 Square Meter 0.325 32.907875 0.76 76.9538 - - 0.325 32.907875
4 Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 10.3295 Cubic Meter 2.96 30.57532 - - 1.05 10.845975 0.35 3.615325
5 Plastering (AR1014i) : 16mm thick cement Plaster in CM (1:6) over brick work in outside (outside) - 16mm thick cement Plaster in CM (1:6) over brick work in outside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 471.51 Square Meter 0.24 113.1624 - - 0.16 75.4416 - -
6 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 73.776 Square Meter 0.17 12.54192 - - 0.14 10.32864 - -
7 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 180.414 Square Meter 0.057 10.283598 - - 0.05 9.0207 - -
8 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 1145.931 Square Meter 0.11776344086022 134.94877754839 - - - - 0.10776344086022 123.48946754839
Total Qty 343.47795506452 177.78106256125 87.928646625767 105.636915
Rate Per Man Day 462 612 512 562
Total Amount 158686.81523981 108802.01028749 45019.467072393 59367.94623
Total Labour Amount (in Rs.): 371876.23882968
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM149 BRMMR0024 BRMMR0023 BRMMR0022 BRMMR0021 BRMMR0020 BRM124 BRMMR0027 CON026 BRM340 BRM028 BRMMR0025 BRM005 BRMMR0038 BRM255 BRM253
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Roofing (AR1132) :.Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 42.12 Sqm 1 42.12 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Other Building Items. (AR1911) :.Stainless steel of 304 grade in hand railing using 50mm dia of 2mm - Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @ 0.90mtr. C/C and stainless square pipe bracing of size 32mm x 32mm x 2mm in 3 rows in staircase as per approved design and specification, buffing, polishing etc with cost,conveyance, taxes of all materials, labour,T&P etc. required for the complete in all respect. and as per direction of Engineer in Charge 40.2 Rmt - - 0.30674846625767 12.331288343558 10.478527607362 421.23680981595 5.101226993865 205.06932515337 1.8773006134969 75.467484662577 3.5 140.7 - - - - - - - - - - - - - - - - - - - -
3 Flooring (AR0817al) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Granite Tiles Above 0.10 Sqm Above 0.10 Sqm & up to 0.4 sqm (10mm. thick) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Granite tiles including rubbing and polishing complete including cost of precast tiles. 101.255 Sqm - - - - - - - - - - - - 1 101.255 1 101.255 0.1375 13.9225625 0.1375 13.9225625 0.015 1.518825 - - - - - - - - - -
4 Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 10.3295 Cum - - - - - - - - - - - - - - - - - - 0.672 6.941424 0.28 2.89226 1 10.3295 350 3615.325 - - - - - -
5 Plastering (AR1014i) :.16mm thick cement Plaster in CM (1:6) over brick work in outside (outside) - 16mm thick cement Plaster in CM (1:6) over brick work in outside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 471.51 Sqm - - - - - - - - - - - - - - - - - - 0.043 20.27493 0.018 8.48718 - - - - - - - - - -
6 Plastering (AR1027) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 73.776 Sqm - - - - - - - - - - - - - - - - - - 0.0372 2.7444672 0.0075 0.55332 - - - - - - - - - -
7 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 180.414 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - 0.8 144.3312 - - - -
8 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 1145.931 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.125 143.241375 0.090322580645161 103.50344516129
Total Qty 42.12 12.331288343558 421.23680981595 205.06932515337 75.467484662577 140.7 101.255 101.255 13.9225625 43.8833837 13.451585 10.3295 3615.325 144.3312 143.241375 103.50344516129
Rate Per Unit 315.644462 178.42 10 256.62 256.62 240.24 1337.6711111 8.5 0 568.667 417.99 33 5.8946 30 193.24787 155.84787
Total Amount 13294.94473944 2200.1484662577 4212.3680981595 52624.890220859 19366.46591411 33801.768 135445.88835443 860.6675 0 24955.032158528 5622.62801415 340.8735 21310.894745 4329.936 27681.090614621 16130.791466049
Total Material Amount (in Rs.): 362178.38779161
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM149 BRM124 BRM340 BRM028 BRM005 BRM255 BRM253
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Roofing (AR1132) :.Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 42.12 Sqm 1 42.12 - - - - - - - - - - - -
2 Other Building Items. (AR1911) :.Stainless steel of 304 grade in hand railing using 50mm dia of 2mm - Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @ 0.90mtr. C/C and stainless square pipe bracing of size 32mm x 32mm x 2mm in 3 rows in staircase as per approved design and specification, buffing, polishing etc with cost,conveyance, taxes of all materials, labour,T&P etc. required for the complete in all respect. and as per direction of Engineer in Charge 40.2 Rmt - - - - - - - - - - - - - -
3 Flooring (AR0817al) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Granite Tiles Above 0.10 Sqm Above 0.10 Sqm & up to 0.4 sqm (10mm. thick) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Granite tiles including rubbing and polishing complete including cost of precast tiles. 101.255 Sqm - - 1 101.255 0.1375 13.9225625 0.015 1.518825 - - - - - -
4 Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 10.3295 Cum - - - - 0.672 6.941424 0.28 2.89226 350 3615.325 - - - -
5 Plastering (AR1014i) :.16mm thick cement Plaster in CM (1:6) over brick work in outside (outside) - 16mm thick cement Plaster in CM (1:6) over brick work in outside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 471.51 Sqm - - - - 0.043 20.27493 0.018 8.48718 - - - - - -
6 Plastering (AR1027) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 73.776 Sqm - - - - 0.0372 2.7444672 0.0075 0.55332 - - - - - -
7 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 180.414 Sqm - - - - - - - - - - - - - -
8 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 1145.931 Sqm - - - - - - - - - - 0.125 143.241375 0.090322580645161 103.50344516129
Total Qty 42.12 101.255 43.8833837 13.451585 3615.325 143.241375 103.50344516129
Rate Per Unit 0 16.45 0 274.25 0 0 0
Total Amount 0 1665.64475 0 3689.09718625 0 0 0
Total Royalty Amount (in Rs.): 5354.74193625
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 1500 Rs. 1500
2 Any Other Lumpsum @ Rs. 8971 Rs. 8971
3 Contingency @ 1% Rs. 7511.4253642445
Total Addition Component Amount (in Rs.): 17982.425364245
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 7511.42 Rs. 7511.42
2 Royalty @ Rs. 1919.1922141304 Rs. 1919.1922141304
3 Additional Royalty @ Rs. 3147.67089 Rs. 3147.67089
4 EMF @ Rs. 95.959610706522 Rs. 95.959610706522
5 DMF @ Rs. 191.91922141304 Rs. 191.91922141304
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 351.105 Rs. 351.105
7 Labour Cess @ 1% Rs. 7691.2496178869
Total Deduction Component Amount (in Rs.): 20908.516554137
Total Net Amount (in Rs.): 748216.44523455