Final Dpr

State: Odisha District: Rayagada Block: Bissamcuttack Gram Panchayat: Raskola
Work Code: OD/370/3547/121123/425331/00065546 (CONSTRUCTION OF CC ROAD AT TADO)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Bissamcuttack Bill Status: Final Bill
Proposal Date: - Date of Commencement: 04-12-2025
Date of Completion: 11-12-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: SRINIVAS MAHANTY
Administrative Approval Details
Approval No.: OD/370/3547/121123/425331/00065546/AS
Technical Sanction Details
Technical Sanction No.: OD/370/3547/121123/425331/00065546/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 12.8625 240.77592 3096.980271
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 12.8625 519.446232 6681.3771591
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 9.8 216.23489289764 2119.1019503969
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 25.725 5227.50850192 134477.65621189
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 21.86625 6806.69795304 148836.95911566
Total Amount (in Rs.): 295212.07470805
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled Skilled
Rs. 462 Rs. 512 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 12.8625 Cubic Meter 0.516 6.63705 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 12.8625 Cubic Meter 0.1236 1.589805 - - - -
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 9.8 Square Meter - - 0.05 0.49 0.05 0.49
4 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.725 Cubic Meter 3.9 100.3275 - - 0.18 4.6305
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 21.86625 Cubic Meter 4.6 100.58475 - - 0.68 14.86905
Total Qty 209.139105 0.49 19.98955
Rate Per Man Day 462 512 562
Total Amount 96622.26651 250.88 11234.1271
Total Labour Amount (in Rs.): 108107.27361
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM104 BRM092 BRM340 BRM028 BRM044 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 12.8625 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 12.8625 Cum 1 12.8625 - - - - - - - - - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 9.8 Sqm - - 0.00267 0.026166 0.126 1.2348 - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.725 Cum - - - - - - 2.29 58.91025 0.48 12.348 0.96 24.696 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 21.86625 Cum - - - - - - 3.23 70.6279875 0.45 9.8398125 - - 0.9 19.679625
Total Qty 12.8625 0.026166 1.2348 129.5382375 22.1878125 24.696 19.679625
Rate Per Unit 347.95 58573.086 229.106 600.692 417.99 1291.11 1737.73
Total Amount 4475.506875 1532.623368276 282.9000888 77812.58296035 9274.283746875 31885.25256 34197.87475125
Total Material Amount (in Rs.): 159461.02435055
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM104 BRM092 BRM340 BRM028 BRM044 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 12.8625 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 12.8625 Cum 1 12.8625 - - - - - - - - - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 9.8 Sqm - - 0.00267 0.026166 0.000614 0.0060172 - - - - - - - -
4 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 25.725 Cum - - - - - - 2.29 58.91025 0.48 12.348 0.96 24.696 - -
5 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 21.86625 Cum - - - - - - 3.23 70.6279875 0.45 9.8398125 - - 0.9 19.679625
Total Qty 12.8625 0.026166 0.0060172 129.5382375 22.1878125 24.696 19.679625
Rate Per Unit 109.25 0 0 0 109.25 176.8 176.8
Total Amount 1405.228125 0 0 0 2424.018515625 4366.2528 3479.3577
Total Royalty Amount (in Rs.): 11674.857140625
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 1834 Rs. 1834
2 Contingency @ 1% Rs. 2952.1207470805
Total Addition Component Amount (in Rs.): 4786.1207470805
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ 1% Rs. 2999.9819545513
2 Royalty @ Rs. 6995.5921875 Rs. 6995.5921875
3 Additional Royalty @ Rs. 3629.926125 Rs. 3629.926125
4 EMF @ Rs. 349.779609375 Rs. 349.779609375
5 DMF @ Rs. 699.55921875 Rs. 699.55921875
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 142 x 3.945) @ 1025.7 Rs. 1025.7
7 Labour Cess @ 1% Rs. 2999.9819545513
Total Deduction Component Amount (in Rs.): 18700.521049728
Total Net Amount (in Rs.): 281297.6744054