Final Dpr

State: Odisha District: Cuttack Block: Nischinta Koili Gram Panchayat: Babujanga
Work Code: OD/350/3342/117077/399988/00066058 (Improvement of road from Jogendra Beura house to Bhakta Mohanty house of Babujanga GP.)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Nischinta Koili Bill Status: Final Bill
Proposal Date: 08-04-2021 Date of Commencement: 26-11-2025
Date of Completion: 26-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: Binay Ranjan Sahoo
Administrative Approval Details
Approval No.: OD/350/3342/117077/399988/00066058/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3342/117077/399988/00066058/TS
Fund Sanction No.: 9114
Fund Sanction Amount (in Rs.): 400000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 11.35333212864 240.77592 2733.6089883389
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 16.13041168464 529.647232 8543.42789979
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 27.97093435728 5823.03464436 162875.71979756
4 Concrete (AR0307) : First floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 27.22890394 7688.49746932 209349.35903505
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 42.71865746 216.23489289764 9237.2643205941
Total Amount (in Rs.): 392739.38004133
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 11.35333212864 Cubic Meter 0.516 5.8583193783782 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.13041168464 Cubic Meter 0.1236 1.9937188842215 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 27.97093435728 Cubic Meter 3.9 109.08664399339 - - 0.18 5.0347681843104
4 Concrete (AR0307) : First floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 27.22890394 Cubic Meter 5.29 144.0409018426 - - 0.782 21.29300288108
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 42.71865746 Square Meter - - 0.05 2.135932873 0.05 2.135932873
Total Qty 260.97958409859 28.46370393839 2.135932873
Rate Per Man Day 462 562 512
Total Amount 120572.56785355 15996.601613375 1093.597630976
Total Labour Amount (in Rs.): 137662.7670979
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 11.35333212864 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.13041168464 Cum 1 16.13041168464 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 27.97093435728 Cum - - 2.29 64.053439678171 0.48 13.426048491494 0.96 26.852096982989 - - - - - -
4 Concrete (AR0307) :.First floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 27.22890394 Cum - - 3.23 87.9493597262 0.45 12.253006773 - - 0.9 24.506013546 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 42.71865746 Sqm - - - - - - - - - - 0.00267 0.1140588154182 0.126 5.38255083996
Total Qty 16.13041168464 152.00279940437 25.679055264494 26.852096982989 24.506013546 0.1140588154182 5.38255083996
Rate Per Unit 413.05 569.712 417.99 2038.31 2466.91 58573.086 229.106
Total Amount 6662.6665463406 86597.818854263 10733.588310006 54732.897801396 60454.129876763 6680.7768045484 1233.1746927399
Total Material Amount (in Rs.): 227095.05288606
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 11.35333212864 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.13041168464 Cum 1 16.13041168464 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 27.97093435728 Cum - - 2.29 64.053439678171 0.48 13.426048491494 0.96 26.852096982989 - - - - - -
4 Concrete (AR0307) :.First floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 27.22890394 Cum - - 3.23 87.9493597262 0.45 12.253006773 - - 0.9 24.506013546 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 42.71865746 Sqm - - - - - - - - - - 0.00267 0.1140588154182 0.000614 0.02622925568044
Total Qty 16.13041168464 152.00279940437 25.679055264494 26.852096982989 24.506013546 0.1140588154182 0.02622925568044
Rate Per Unit 54.25 0 54.25 158.5 158.5 0 0
Total Amount 875.07483389172 0 1393.0887480988 4256.0573718037 3884.203147041 0 0
Total Royalty Amount (in Rs.): 10408.424100835
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 2000 Rs. 2000
2 Any Other Lumpsum @ Rs. 1260.57 Rs. 1260.57
3 Contingency @ Rs. 4000 Rs. 4000
Total Addition Component Amount (in Rs.): 7260.57
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 4000 Rs. 4000
2 Royalty @ Rs. 8139.8857119882 Rs. 8139.8857119882
3 Additional Royalty @ Rs. 1047.5555320488 Rs. 1047.5555320488
4 EMF @ Rs. 406.99428559941 Rs. 406.99428559941
5 DMF @ Rs. 813.98857119883 Rs. 813.98857119883
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 1203.225 Rs. 1203.225
7 Labour Cess @ Rs. 4000 Rs. 4000
8 Any Other Lumpsum Bill @ Rs. 8000 Rs. 8000
Total Deduction Component Amount (in Rs.): 27611.649100835
Total Net Amount (in Rs.): 372388.3009405