Final Dpr

State: Odisha District: Jajpur Block: Bari Gram Panchayat: Mandari
Work Code: OD/356/3395/118293/402057/00066868 (Repair and Restoration of CC road from RD road to Jena Sahi)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Bari Bill Status: Final Bill
Proposal Date: - Date of Commencement: 05-12-2025
Date of Completion: 05-01-2026 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Swarnapriya Nayak
Administrative Approval Details
Approval No.: OD/356/3395/118293/402057/00066868/AS
Technical Sanction Details
Technical Sanction No.: OD/356/3395/118293/402057/00066868/TS
Fund Sanction No.: 8053
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 25.48512 7473.85682442 190472.13803316
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 13.93545 216.23489289764 3013.3305382304
Total Amount (in Rs.): 193485.46857139
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 25.48512 Cubic Meter 4.6 117.231552 - - 0.68 17.3298816
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 13.93545 Square Meter - - 0.05 0.6967725 0.05 0.6967725
Total Qty 117.231552 18.0266541 0.6967725
Rate Per Man Day 462 562 512
Total Amount 54160.977024 10130.9796042 356.74752
Total Labour Amount (in Rs.): 64648.7041482
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM057 BRM340 BRM028 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 25.48512 Cum 0.9 22.936608 3.23 82.3169376 0.45 11.468304 - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 13.93545 Sqm - - - - - - 0.00267 0.0372076515 0.126 1.7558667
Total Qty 22.936608 82.3169376 11.468304 0.0372076515 1.7558667
Rate Per Unit 2025.41 568.667 873.69 58573.086 229.106
Total Amount 46456.03520928 46810.925954179 10019.74252176 2179.3669711675 402.2795961702
Total Material Amount (in Rs.): 105868.35025256
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM057 BRM340 BRM028 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 25.48512 Cum 0.9 22.936608 3.23 82.3169376 0.45 11.468304 - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 13.93545 Sqm - - - - - - 0.00267 0.0372076515 0.000614 0.0085563663
Total Qty 22.936608 82.3169376 11.468304 0.0372076515 0.0085563663
Rate Per Unit 444.5 0 274.25 0 0
Total Amount 10195.322256 0 3145.182372 0 0
Total Royalty Amount (in Rs.): 13340.504628
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 2654 Rs. 2654
2 Any Other Lumpsum @ Rs. 1860 Rs. 1860
3 Contingency @ Rs. 2000 Rs. 2000
Total Addition Component Amount (in Rs.): 6514
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 2000 Rs. 2000
2 Royalty @ Rs. 3383.14968 Rs. 3383
3 Additional Royalty @ Rs. 9449.882496 Rs. 9450
4 EMF @ Rs. 169.157484 Rs. 169
5 DMF @ Rs. 338.314968 Rs. 338
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 650.925 Rs. 650.925
7 Labour Cess @ Rs. 2000 Rs. 2000
Total Deduction Component Amount (in Rs.): 17990.925
Total Net Amount (in Rs.): 182008.54357139