Final Dpr

State: Odisha District: Kendujhar Block: Champua Gram Panchayat: Sunaposi
Work Code: OD/361/3445/119307/385414/00072132 (Construction of CC Road from RD Road to Sukadev Mahanta House village-Indraprastha, GP-Sunaposi)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Champua Bill Status: 1st Bill
Proposal Date: 17-05-2022 Date of Commencement: 15-01-2026
Date of Completion: - Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Bebina Tarai
Administrative Approval Details
Approval No.: OD/361/3445/119307/385414/00072132/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3445/119307/385414/00072132/TS
Fund Sanction No.: 140/ZP
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 6.32511792 240.77592 1522.9360862965
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 16.79109467 927.950832 15581.310269217
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 26.52173271 6033.67457624 160023.50437016
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 14.508101125 7716.93134888 111958.02038423
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 18.9516 216.23489289764 4097.9971962389
Total Amount (in Rs.): 293183.76830615
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.32511792 Cubic Meter 0.516 3.26376084672 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.79109467 Cubic Meter 0.1236 2.075379301212 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.52173271 Cubic Meter 3.9 103.434757569 - - 0.18 4.7739118878
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.508101125 Cubic Meter 4.6 66.737265175 - - 0.68 9.865508765
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 18.9516 Square Meter - - 0.05 0.94758 0.05 0.94758
Total Qty 175.51116289193 15.5870006528 0.94758
Rate Per Man Day 462 562 512
Total Amount 81086.157256073 8759.8943668736 485.16096
Total Labour Amount (in Rs.): 90331.212582946
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.32511792 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.79109467 Cum 1 16.79109467 - - - - - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.52173271 Cum - - 2.29 60.7347679059 0.48 12.7304317008 0.96 25.4608634016 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.508101125 Cum - - 3.23 46.86116663375 0.45 6.52864550625 - - 0.9 13.0572910125 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 18.9516 Sqm - - - - - - - - - - 0.00267 0.050600772 0.126 2.3879016
Total Qty 16.79109467 107.59593453965 19.25907720705 25.4608634016 13.0572910125 0.050600772 2.3879016
Rate Per Unit 591.41 598.252 601.41 1351.51 1971.51 58573.086 229.106
Total Amount 9930.4212987847 64369.483030215 11582.601623092 34410.611495896 25742.579804054 2963.8433700224 547.0825839696
Total Material Amount (in Rs.): 149546.62320603
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.32511792 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.79109467 Cum 1 16.79109467 - - - - - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.52173271 Cum - - 2.29 60.7347679059 0.48 12.7304317008 0.96 25.4608634016 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.508101125 Cum - - 3.23 46.86116663375 0.45 6.52864550625 - - 0.9 13.0572910125 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 18.9516 Sqm - - - - - - - - - - 0.00267 0.050600772 0.000614 0.0116362824
Total Qty 16.79109467 107.59593453965 19.25907720705 25.4608634016 13.0572910125 0.050600772 0.0116362824
Rate Per Unit 270.25 0 270.25 782.5 782.5 0 0
Total Amount 4537.7933345675 0 5204.7656152053 19923.125611752 10217.330217281 0 0
Total Royalty Amount (in Rs.): 39883.014778806
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 2762 Rs. 2762
2 Any Other Lumpsum @ Rs. 1053 Rs. 1053
3 Contingency @ Rs. 3000 Rs. 3000
Total Addition Component Amount (in Rs.): 6815
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
1 Contingency @ Rs. 3000 Rs. 3000
2 Royalty @ Rs. 6269.1160895297 Rs. 6269
3 Additional Royalty @ Rs. 32673.531275847 Rs. 32674
4 EMF @ Rs. 313.45580447649 Rs. 313
5 DMF @ Rs. 626.91160895297 Rs. 627
6 Empty Gunny Bag (Cement x Gunny Bag Rate : 0 x 3.945) @ 852.12 Rs. 852.12
7 Labour Cess @ Rs. 3000 Rs. 3000
8 Any Other Lumpsum Bill @ Rs. 6000 Rs. 6000
Total Deduction Component Amount (in Rs.): 52735.12
Total Net Amount (in Rs.): 247263.64830615