Labour Statement

State: Odisha District: Malkangiri Block: Malkangiri Gram Panchayat: Matapaka
Work Code: OD/364/3484/119972/430280/00013434 (Construction of Market Complex at Matapaka)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Malkangiri Bill Status: Final Bill
Proposal Date: 19-02-2024 Date of Commencement: 10-12-2024
Date of Completion: 30-12-2024 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Creation of Capital Asset for Revenue Generation Project Sub-Category: Market Complex
Project Type: New Work Name of Executant: TAPAN KUMAR SAMAL
Administrative Approval Details
Approval No.: OD/364/3484/119972/430280/00013434/AS
Technical Sanction Details
Technical Sanction No.: OD/364/3484/119972/430280/00013434/TS
Fund Sanction No.: 12821
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
Rs. 452 Rs. 552 Rs. 602 Rs. 502
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0122Ai1) : Earthwork in all kinds of soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth - Earthwork in all kinds of soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 16.77 Cubic Meter 0.503534 8.44426518 - - - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 21.796 Cubic Meter 3.9 85.0044 - - 0.18 3.92328 - -
3 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 25 Quintal 0.8 20 0.044 1.1 - - 0.3 7.5
4 Masonry Brick Work (AR0603di) : C.B. Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure - Brickwork with C.B. Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 0 Cubic Meter 2.82 0 - - 1.05 0 0.35 0
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 26 Square Meter 0.36 9.36 - - - - 0.13 3.38
6 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 43.2 Square Meter 0.24 10.368 - - 0.16 6.912 - -
7 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 128.0125 Square Meter 0.12 15.3615 - - 0.14 17.92175 - -
8 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 199 Square Meter 0.062 12.338 - - - - 0.052 10.348
9 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 199 Square Meter 0.053763440860215 10.698924731183 - - - - 0.053763440860215 10.698924731183
10 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 5.9 Quintal 6.3976377952756 37.746062992126 1.9685039370079 11.614173228346 3.9370078740157 23.228346456693 3.4448818897638 20.324803149606
11 R.C.C. Work (AR0405Ac) : Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-25 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work, etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 28.81845 Cubic Meter 1.3333 38.423639385 5.29605 152.6239521225 5.33875 153.8544999375 - -
Total Qty 247.74479228831 205.83987639419 52.251727880789 165.33812535085
Rate Per Man Day 452 552 602 502
Total Amount 111980.64611432 113623.61176959 31455.540184235 82999.738926125
Total Labour Amount (in Rs.): 340059.53699427