Labour Statement

State: Odisha District: Kandhamal Block: Phulbani Gram Panchayat: Gumagarh
Work Code: OD/359/3430/118982/415563/00013526 (Imp. Of Gumagarh Tank)
Project Category: Water Body
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Phulbani Bill Status: Final Bill
Proposal Date: 20-04-2021 Date of Commencement: 22-07-2025
Date of Completion: 24-08-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Capital Assets Project Sub-Category: Tank
Project Type: Renovation or Rejuvenation Name of Executant: ANANDA KUMAR MEHER
Administrative Approval Details
Approval No.: OD/359/3430/118982/415563/00013526/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3430/118982/415563/00013526/TS
Fund Sanction No.: 3289
Fund Sanction Amount (in Rs.): 500000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.5074344 Cubic Meter 0.516 18.8378361504 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 20.96053143872 Cubic Meter 0.1236 2.5907216858258 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 69.779868766515 Cubic Meter 3.9 272.14148818941 - - 0.18 12.560376377973
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 6.45298529472 Cubic Meter 4.6 29.683732355712 - - 0.68 4.3880300004096
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 136.020397136 Square Meter - - 0.05 6.8010198568 0.05 6.8010198568
Total Qty 323.25377838135 23.749426235182 6.8010198568
Rate Per Man Day 462 562 512
Total Amount 149343.24561218 13347.177544172 3482.1221666816
Total Labour Amount (in Rs.): 166172.54532304