Labour Statement

State: Odisha District: Kendujhar Block: Kendujhar Sadar Gram Panchayat: Dimbo
Work Code: OD/361/3452/119452/386174/00013821 (Construction of CC road from Indra sahu house incomplete road to Community center near Mission sakti Gruha)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Kendujhar Sadar Bill Status: Final Bill
Proposal Date: 10-05-2023 Date of Commencement: 06-03-2025
Date of Completion: 04-04-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Manoj Kumar Sahoo
Administrative Approval Details
Approval No.: OD/361/3452/119452/386174/00013821/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3452/119452/386174/00013821/TS
Fund Sanction No.: 12942
Fund Sanction Amount (in Rs.): 172711
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 452 Rs. 552 Rs. 502
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.7909116 Cubic Meter 0.516 1.9561103856 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.3854129344 Cubic Meter 0.1236 1.2836370386918 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 12.48286945888 Cubic Meter 3.9 48.683190889632 - - 0.18 2.2469165025984
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 10.1090976 Cubic Meter 4.6 46.50184896 - - 0.68 6.874186368
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 27.6386425 Square Meter - - 0.05 1.381932125 0.05 1.381932125
Total Qty 98.424787273924 10.503034995598 1.381932125
Rate Per Man Day 452 552 502
Total Amount 44488.003847814 5797.6753175703 693.72992675
Total Labour Amount (in Rs.): 50979.409092134