Labour Statement

State: Odisha District: Kendujhar Block: Kendujhar Sadar Gram Panchayat: Maidankel
Work Code: OD/361/3452/119460/386089/00013825 (Improvement of road from Kirtan mandap to darsan sahi)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Kendujhar Sadar Bill Status: Final Bill
Proposal Date: 19-07-2022 Date of Commencement: 03-05-2025
Date of Completion: 19-05-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: CC Road
Project Type: Repair and Maintenance Name of Executant: Ranjan Kumar Swain
Administrative Approval Details
Approval No.: OD/361/3452/119460/386089/00013825/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3452/119460/386089/00013825/TS
Fund Sanction No.: 310
Fund Sanction Amount (in Rs.): 400000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 5.875736 Cubic Meter 0.516 3.031879776 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 22.46088576 Cubic Meter 0.1236 2.776165479936 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 32.28539952 Cubic Meter 3.9 125.913058128 - - 0.18 5.8113719136
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 21.529617 Cubic Meter 4.6 99.0362382 - - 0.68 14.64013956
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 58.064375 Square Meter - - 0.05 2.90321875 0.05 2.90321875
Total Qty 230.75734158394 23.3547302236 2.90321875
Rate Per Man Day 462 562 512
Total Amount 106609.89181178 13125.358385663 1486.448
Total Labour Amount (in Rs.): 121221.69819744