Labour Statement

State: Odisha District: Rayagada Block: Rayagada Gram Panchayat: Karlakana
Work Code: OD/370/3557/121263/426287/00016768 (Construction of CC road at Karlakona(phase-2))
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Rayagada Bill Status: Final Bill
Proposal Date: - Date of Commencement: 02-05-2025
Date of Completion: 29-05-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: BHRAMAR BARA KISHAN
Administrative Approval Details
Approval No.: OD/370/3557/121263/426287/00016768/AS
Technical Sanction Details
Technical Sanction No.: OD/370/3557/121263/426287/00016768/TS
Fund Sanction No.: 2644
Fund Sanction Amount (in Rs.): 179005
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
Rs. 452 Rs. 552
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 25.05 Cubic Meter 0.43 10.7715 - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.432 Cubic Meter 0.1236 1.1657952 - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 19.26 Cubic Meter 3.9 75.114 0.18 3.4668
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.306 Cubic Meter 4.6 42.8076 0.68 6.32808
Total Qty 129.8588952 9.79488
Rate Per Man Day 452 552
Total Amount 58696.2206304 5406.77376
Total Labour Amount (in Rs.): 64102.9943904