Labour Statement

State: Odisha District: Boudh Block: Boudh Gram Panchayat: Khuntabandha
Work Code: OD/349/3329/116783/418325/00016842 (Improvement of road from Gobindpur to Gingira sahi)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Boudh Bill Status: Final Bill
Proposal Date: - Date of Commencement: 23-03-2025
Date of Completion: 19-08-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES Project Sub-Category: CC Road
Project Type: Repair and Maintenance Name of Executant: Srija Bharati
Administrative Approval Details
Approval No.: OD/349/3329/116783/418325/00016842/AS
Technical Sanction Details
Technical Sanction No.: OD/349/3329/116783/418325/00016842/TS
Fund Sanction No.: 4921
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 452 Rs. 552 Rs. 502
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 7.1875 Cubic Meter 0.43 3.090625 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 21.275 Cubic Meter 0.1236 2.62959 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 28.4625 Cubic Meter 3.9 111.00375 - - 0.18 5.12325
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 17.02 Cubic Meter 4.6 78.292 - - 0.68 11.5736
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 43.7 Square Meter - - 0.05 2.185 0.05 2.185
Total Qty 195.015965 18.88185 2.185
Rate Per Man Day 452 552 502
Total Amount 88147.21618 10422.7812 1096.87
Total Labour Amount (in Rs.): 99666.86738