Labour Statement

State: Odisha District: Ganjam Block: Digapahandi Gram Panchayat: Padmanavapur
Work Code: OD/354/3372/117743/412776/00017439 (Construction of CC road from village to odia Sahi at P.N.Pur)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Digapahandi Bill Status: Final Bill
Proposal Date: 07-01-2023 Date of Commencement: 16-08-2025
Date of Completion: 29-10-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: Pavor Block
Project Type: New Work Name of Executant: SUNAYANA PANIGRAHI
Administrative Approval Details
Approval No.: OD/354/3372/117743/412776/00017439/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3372/117743/412776/00017439/TS
Fund Sanction No.: 13745
Fund Sanction Amount (in Rs.): 700000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 66.1505288 Cubic Meter 0.1236 8.17620535968 - - - -
2 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 151.081632 Cubic Meter 0.516 77.958122112 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 33.775463 Cubic Meter 3.9 131.7243057 - - 0.18 6.07958334
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 252.636 Square Meter - - 0.05 12.6318 0.05 12.6318
Total Qty 217.85863317168 18.71138334 12.6318
Rate Per Man Day 462 562 512
Total Amount 100650.68852532 10515.79743708 6467.4816
Total Labour Amount (in Rs.): 117633.9675624