Labour Statement

State: Odisha District: Ganjam Block: Patrapur Gram Panchayat: Tandipur
Work Code: OD/354/3379/117894/413152/00017491 (IMPROVEMENT OF ROAD WITH CC /PAVER BLOCK WITH CD WORKS TANDIPUR FROM RD TO TANDIPUR SIVA MANDIRA ROAD)
Project Category: Road
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Patrapur Bill Status: Final Bill
Proposal Date: 25-11-2021 Date of Commencement: 15-09-2025
Date of Completion: 31-10-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: Pavor Block
Project Type: New Work Name of Executant: SUNIL KUMAR JANI
Administrative Approval Details
Approval No.: OD/354/3379/117894/413152/00017491/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3379/117894/413152/00017491/TS
Fund Sanction No.: 12614
Fund Sanction Amount (in Rs.): 603632
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled Skilled
Rs. 462 Rs. 512 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
2 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 42.446599 Cubic Meter 0.516 21.902445084 - - - -
3 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 34.7765225 Cubic Meter 0.1236 4.298378181 - - - -
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 149.8726 Square Meter - - 0.05 7.49363 0.05 7.49363
5 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 18.492349 Cubic Meter 3.9 72.1201611 - - 0.18 3.32862282
Total Qty 98.320984365 7.49363 10.82225282
Rate Per Man Day 462 512 562
Total Amount 45424.29477663 3836.73856 6082.10608484
Total Labour Amount (in Rs.): 55343.13942147