Labour Statement

State: Odisha District: Khordha Block: Bhubaneswar Gram Panchayat: Dadha
Work Code: OD/362/3460/119602/407513/00017647 (Construction of cc Road from Marichia Bhagabat Ghara to Transformer, Dadha GP)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Bhubaneswar Bill Status: Final Bill
Proposal Date: - Date of Commencement: 20-05-2025
Date of Completion: 28-05-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Suchismita Mohanty
Administrative Approval Details
Approval No.: OD/362/3460/119602/407513/00017647/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3460/119602/407513/00017647/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 175000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 612 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.086969 Cubic Meter 0.1236 1.2467493684 - - - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.45614336 Cubic Meter 3.9 52.478959104 - - 0.18 2.4221058048 - -
3 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.3489 Cubic Meter 0.516 1.2120324 - - - - - -
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.27574976 Cubic Meter 4.6 51.868448896 - - 0.68 7.6675098368 - -
5 Masonry Stone Work (AR0717) : Laterite stone masonry - Laterite stone masonry in cement mortar (1:6) in foundation and plinth cost conveyance, royalty, taxes of all materials, labor, required for the work, etc. complete and as per direction of the Engineer-in-charge. 1.233479808 Cubic Meter 1.21 1.49251056768 1.41 1.73920652928 1.05 1.2951537984 2.295 2.83083615936
Total Qty 108.29870033608 11.38476944 2.83083615936 1.73920652928
Rate Per Man Day 462 562 612 512
Total Amount 50033.999555269 6398.24042528 1732.4717295283 890.47374299136
Total Labour Amount (in Rs.): 59055.185453069