Labour Statement

State: Odisha District: Sundargarh Block: Gurundia Gram Panchayat: Kundheidiha
Work Code: OD/373/3577/121585/385038/00028241 (Repair and Maintenance of Govt. Primary School, Kundheidiha)
Project Category: Building
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Gurundia Bill Status: Final Bill
Proposal Date: - Date of Commencement: 13-10-2025
Date of Completion: 06-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Primary School Building Project Sub-Category: Elementary School
Project Type: Repair and Maintenance Name of Executant: Sumanti Kullu
Administrative Approval Details
Approval No.: OD/373/3577/121585/385038/00028241/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3577/121585/385038/00028241/TS
Fund Sanction No.: 28923
Fund Sanction Amount (in Rs.): 400000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Highly-Skilled Un-Skilled Semi-Skilled Skilled
Rs. 612 Rs. 462 Rs. 512 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 7.638 Square Meter 0.325 2.48235 0.76 5.80488 - - 0.325 2.48235
2 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 107.79 Square Meter 0.216 23.28264 - - - - 0.216 23.28264
3 Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 165 Square Meter 0.21505376344086 35.483870967742 - - - - 0.16129032258065 26.612903225806
4 Masonry Brick Work (AR0603ci) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 3.0084 Cubic Meter 2.96 8.904864 - - 1.05 3.15882 0.35 1.05294
5 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 26.16 Square Meter 0.12 3.1392 - - 0.14 3.6624 - -
6 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 304.095 Square Meter 0.053763440860215 16.349193548387 - - - - 0.053763440860215 16.349193548387
7 Painting (AR0920) : Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 165.175 Square Meter 0.064 10.5712 - - - - 0.054 8.91945
8 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 192.425 Square Meter 0.11776344086022 22.660630107527 - - - - 0.10776344086022 20.736380107527
9 Painting (AR0901b) : Priming one coat in inner surface with primer of approved quality over iron work. - Priming one coat in inner surface with primer of approved quality over iron work including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 18.55 Square Meter 0.053763440860215 0.99731182795699 - - - - 0.053763440860215 0.99731182795699
10 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 0.1855 Quintal 6.3976377952756 1.1867618110236 1.9685039370079 0.36515748031496 3.9370078740157 0.73031496062992 3.4448818897638 0.63902559055118
Total Qty 101.07219430023 125.05802226264 6.170037480315 7.5515349606299
Rate Per Man Day 612 462 512 562
Total Amount 61856.18291174 57776.806285338 3159.0591899213 4243.962647874
Total Labour Amount (in Rs.): 127036.01103487