Labour Statement

State: Odisha District: Kendujhar Block: Ghasipura Gram Panchayat: Batto
Work Code: OD/361/3446/119311/387322/00039119 (Const.of CC Road from Telisahi to Nadighat Godiuparsahi,Karadapal,Batto)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Ghasipura Bill Status: Final Bill
Proposal Date: - Date of Commencement: 25-07-2025
Date of Completion: 06-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Shradhanjali Sahoo
Administrative Approval Details
Approval No.: OD/361/3446/119311/387322/00039119/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3446/119311/387322/00039119/TS
Fund Sanction No.: 1130
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.75 Cubic Meter 0.516 3.483 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 19.71 Cubic Meter 0.1236 2.436156 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.46 Cubic Meter 3.9 103.194 - - 0.18 4.7628
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.5999 Cubic Meter 4.6 62.55954 - - 0.68 9.247932
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 72.36 Square Meter - - 0.05 3.618 0.05 3.618
Total Qty 171.672696 17.628732 3.618
Rate Per Man Day 462 562 512
Total Amount 79312.785552 9907.347384 1852.416
Total Labour Amount (in Rs.): 91072.548936