Labour Statement

State: Odisha District: Balangir Block: Agalpur Gram Panchayat: Salebhata
Work Code: OD/345/3284/115775/419874/00044931 (COMPLETION OF BHOGA MANDAP ATSHIVA MANDIR AT SALEBHATASALEBHATA GP)
Project Category: Religious Structures
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Agalpur Bill Status: Final Bill
Proposal Date: - Date of Commencement: 25-08-2025
Date of Completion: 06-10-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: Religious Structures
Project Type: Completion Name of Executant: Maheshsingh Mahapatra
Administrative Approval Details
Approval No.: OD/345/3284/115775/419874/00044931/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3284/115775/419874/00044931/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Semi-Skilled
Rs. 462 Rs. 612 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 130.714521 Square Meter 0.216 28.234336536 - - 0.216 28.234336536
2 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 272.5101773892 Square Meter 0.11776344086022 32.09173615878 - - 0.10776344086022 29.366634384888
3 Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 5.88819214 Square Meter 0.325 1.9136624455 0.76 4.4750260264 0.325 1.9136624455
4 Site Clearance (AR1403i) : Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials - Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness and as per direction of Engineer-in-Charge (in area of light jungle) 1393.545 Square Meter 0.015 20.903175 0.0006 0.836127 - -
Total Qty 83.14291014028 59.514633366388 5.3111530264
Rate Per Man Day 462 612 512
Total Amount 38412.024484809 36422.955620229 2719.3103495168
Total Labour Amount (in Rs.): 77554.290454555