Labour Statement

State: Odisha District: Ganjam Block: Khallikote Gram Panchayat: Badapalli
Work Code: OD/354/3377/117829/411783/00049581 (CONSTRUCTION OF PAVER ROAD AT KURUMIPUR JANI BARA SAHI GP BADAPALLI 2526)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Khallikote Bill Status: Final Bill
Proposal Date: - Date of Commencement: 04-09-2025
Date of Completion: 15-10-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: Pavor Block
Project Type: New Work Name of Executant: MANORANJAN MALLIK
Administrative Approval Details
Approval No.: OD/354/3377/117829/411783/00049581/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3377/117829/411783/00049581/TS
Fund Sanction No.: 15612
Fund Sanction Amount (in Rs.): 180163
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
Rs. 462 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.3078192 Cubic Meter 0.516 1.1908347072 - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 17.6330978944 Cubic Meter 0.1236 2.1794508997478 - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.69251072 Cubic Meter 3.9 14.400791808 0.18 0.6646519296
Total Qty 17.771077414948 0.6646519296
Rate Per Man Day 462 562
Total Amount 8210.2377657059 373.5343844352
Total Labour Amount (in Rs.): 8583.7721501411