Labour Statement

State: Odisha District: Mayurbhanj Block: Jamda Gram Panchayat: Hensda
Work Code: OD/365/3495/120164/387625/00054887 (Completion of CC road from culvert to Primary school gate at Khairpal)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Jamda Bill Status: 1st Bill
Proposal Date: - Date of Commencement: 10-10-2025
Date of Completion: - Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: DAKTAR NAIK
Administrative Approval Details
Approval No.: OD/365/3495/120164/387625/00054887/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3495/120164/387625/00054887/TS
Fund Sanction No.: 14036
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 4.44505836 Cubic Meter 0.516 2.29365011376 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.27202018 Cubic Meter 0.1236 1.393221694248 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 16.62751218 Cubic Meter 3.9 64.847297502 - - 0.18 2.9929521924
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 10.017634 Cubic Meter 4.6 46.0811164 - - 0.68 6.81199112
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 40.456092 Square Meter - - 0.05 2.0228046 0.05 2.0228046
Total Qty 114.61528571001 11.8277479124 2.0228046
Rate Per Man Day 462 562 512
Total Amount 52952.261998024 6647.1943267688 1035.6759552
Total Labour Amount (in Rs.): 60635.132279992