Labour Statement

State: Odisha District: Kalahandi Block: Madanpur Rampur Gram Panchayat: M.Rampur
Work Code: OD/358/3419/118814/422708/00055148 (CONSTRUTION OF CC ROAD AND DRAIN FROM LALU BARIK GALI TO HARI HAR SAGAR, M.RAMPUR. CR NO- 11/23-24)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Madanpur Rampur Bill Status: Final Bill
Proposal Date: - Date of Commencement: 22-09-2025
Date of Completion: 23-09-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES Project Sub-Category: CC Road
Project Type: New Work Name of Executant: JE NAYAN
Administrative Approval Details
Approval No.: OD/358/3419/118814/422708/00055148/AS
Technical Sanction Details
Technical Sanction No.: OD/358/3419/118814/422708/00055148/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Semi-Skilled Skilled Un-Skilled
Rs. 512 Rs. 562 Rs. 462
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 24 Square Meter - - 0.05 1.2 0.05 1.2
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 8 Cubic Meter 0.1236 0.9888 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 21.85 Cubic Meter 3.9 85.215 - - 0.18 3.933
Total Qty 1.2 5.133 86.2038
Rate Per Man Day 512 562 462
Total Amount 614.4 2884.746 39826.1556
Total Labour Amount (in Rs.): 43325.3016