Labour Statement

State: Odisha District: Kalahandi Block: Lanjigarh Gram Panchayat: Gundri
Work Code: OD/358/3418/118798/423379/00056068 (CONSTRUCTION OF CC ROAD WITH GUARD WALL GUNDRI ROUT PADA TO AWC GUNDRI)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Lanjigarh Bill Status: Final Bill
Proposal Date: - Date of Commencement: 06-10-2025
Date of Completion: 08-01-2026 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD Project Sub-Category: CC Road
Project Type: New Work Name of Executant: BHAWANI SHANKAR SETHI
Administrative Approval Details
Approval No.: OD/358/3418/118798/423379/00056068/AS
Technical Sanction Details
Technical Sanction No.: OD/358/3418/118798/423379/00056068/TS
Fund Sanction No.: 595
Fund Sanction Amount (in Rs.): 700000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 11.07 Cubic Meter 0.516 5.71212 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 2.214 Cubic Meter 0.1236 0.2736504 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 19.0937 Cubic Meter 3.9 74.46543 - - 0.18 3.436866
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 58.712 Square Meter - - 0.05 2.9356 0.05 2.9356
Total Qty 80.4512004 6.372466 2.9356
Rate Per Man Day 462 562 512
Total Amount 37168.4545848 3581.325892 1503.0272
Total Labour Amount (in Rs.): 42252.8076768