Labour Statement

State: Odisha District: Jajpur Block: Bari Gram Panchayat: Dharapur
Work Code: OD/356/3395/118285/402029/00056405 (Completion of Smasana Ghat near Habeli Dhia)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Bari Bill Status: Final Bill
Proposal Date: - Date of Commencement: 03-11-2025
Date of Completion: 02-12-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Saroj Kumar Panda
Administrative Approval Details
Approval No.: OD/356/3395/118285/402029/00056405/AS
Technical Sanction Details
Technical Sanction No.: OD/356/3395/118285/402029/00056405/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 512 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 7.2045765114016 Cubic Meter 1.3333 9.6058618626518 0.0573 0.41282223410331 0.1 0.72045765114016 - -
2 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 46.2511453902 Square Meter - - 0.6547619047619 30.283488053107 0.6547619047619 30.283488053107 - -
3 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 36.1999698202 Square Meter - - 0.30555555555556 11.061101889506 0.30555555555556 11.061101889506 - -
4 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 48.8460376638 Square Meter 0.17 8.303826402846 - - 0.14 6.838445272932 - -
5 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 81.3130534604 Square Meter 0.062 5.0414093145448 - - - - 0.052 4.2282787799408
6 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 5.86 Quintal 0.8 4.688 0.044 0.25784 - - 0.3 1.758
Total Qty 27.639097580043 48.903492866685 42.015252176716 5.9862787799408
Rate Per Man Day 462 562 512 612
Total Amount 12769.26308198 27483.762991077 21511.809114479 3663.6026133238
Total Labour Amount (in Rs.): 65428.437800859