Labour Statement

State: Odisha District: Koraput Block: Bandhugaon Gram Panchayat: Kapalada
Work Code: OD/363/3466/119709/428736/00060640 (Construction of Paver Block at New Street Tikarpoda)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Bandhugaon Bill Status: Final Bill
Proposal Date: 31-12-2024 Date of Commencement: 24-10-2025
Date of Completion: 15-01-2026 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: Pavor Block
Project Type: New Work Name of Executant: Rosan Guria
Administrative Approval Details
Approval No.: OD/363/3466/119709/428736/00060640/AS
Technical Sanction Details
Technical Sanction No.: OD/363/3466/119709/428736/00060640/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled Skilled
Rs. 462 Rs. 512 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 39.1854 Cubic Meter 0.516 20.2196664 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 34.0617 Cubic Meter 0.1236 4.21002612 - - - -
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 35.072 Square Meter - - 0.05 1.7536 0.05 1.7536
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.07488 Cubic Meter 4.6 41.744448 - - 0.68 6.1709184
Total Qty 66.17414052 1.7536 7.9245184
Rate Per Man Day 462 512 562
Total Amount 30572.45292024 897.8432 4453.5793408
Total Labour Amount (in Rs.): 35923.87546104