Labour Statement

State: Odisha District: Puri Block: Satyabadi Gram Panchayat: Sukal
Work Code: OD/369/3546/121105/409700/00061767 (Const of CC Road from GP Road to Crematorium Ground Road)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Satyabadi Bill Status: Final Bill
Proposal Date: 31-12-2024 Date of Commencement: 23-10-2025
Date of Completion: 28-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: NILIMA MOHANTY
Administrative Approval Details
Approval No.: OD/369/3546/121105/409700/00061767/AS
Technical Sanction Details
Technical Sanction No.: OD/369/3546/121105/409700/00061767/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 186532
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
Rs. 462 Rs. 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 44.3475 Cubic Meter 0.1236 5.481351 - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.315 Cubic Meter 3.9 44.1285 0.18 2.0367
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.858 Cubic Meter 4.6 54.5468 0.68 8.06344
Total Qty 104.156651 10.10014
Rate Per Man Day 462 562
Total Amount 48120.372762 5676.27868
Total Labour Amount (in Rs.): 53796.651442