Labour Statement

State: Odisha District: Bargarh Block: Paikmal Gram Panchayat: Bhubaneswarpur
Work Code: OD/347/3320/116536/379718/00064539 (Maintenance of Market Complex at Bhubaneswarpur)
Project Category: Other Infrastructure
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Paikmal Bill Status: Final Bill
Proposal Date: - Date of Commencement: 04-12-2025
Date of Completion: 04-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Capital Assets Project Sub-Category: Rural Haat
Project Type: Repair and Maintenance Name of Executant: Purna Chandra Bariha
Administrative Approval Details
Approval No.: OD/347/3320/116536/379718/00064539/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3320/116536/379718/00064539/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 250000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 612 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 18.830672 Cubic Meter 0.516 9.716626752 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.80002752 Cubic Meter 0.1236 1.334883401472 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.225369600118 Cubic Meter 3.9 55.47894144046 - - 0.18 2.5605665280212 - -
4 Plastering (AR1017) : 20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 11.0090055 Square Meter 0.24 2.64216132 - - 0.16 1.76144088 - -
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 30.52699677 Square Meter 0.36 10.9897188372 - - - - 0.13 3.9685095801
6 Roofing (AR1135i) : G.C.I. Sheet (0.40mm thick) in walling - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in walling including cost of nuts and bolts, fitting, labour and material etc. complete as per direction of Engineer-in-Charge. 41.620544 Square Meter 0.21505376344086 8.9506546236559 - - - - 0.16129032258065 6.7129909677419
7 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.90438272 Cubic Meter 4.6 54.760160512 - - 0.68 8.0949802496 - -
8 Iron Work (AR1703) : Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 2.4546556 Quintal 4.9212598425197 12.079998031496 1.9685039370079 4.8319992125984 4.4291338582677 10.871998228346 - -
Total Qty 155.95314491828 23.288985885968 10.681500547842 4.8319992125984
Rate Per Man Day 462 562 612 512
Total Amount 72050.352952247 13088.410067914 6537.0783352793 2473.9835968504
Total Labour Amount (in Rs.): 94149.824952291