Labour Statement

State: Odisha District: Balangir Block: Gudvella Gram Panchayat: Chinched
Work Code: OD/345/3289/115869/420441/00065274 (Renovation of Lakharpadar Bhangamunda Tank)
Project Category: Water Body
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Gudvella Bill Status: Final Bill
Proposal Date: - Date of Commencement: 03-12-2025
Date of Completion: 04-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance of Capital Assets Project Sub-Category: Tank
Project Type: Renovation or Rejuvenation Name of Executant: SUSHANTA KUMAR BARIK
Administrative Approval Details
Approval No.: OD/345/3289/115869/420441/00065274/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3289/115869/420441/00065274/TS
Fund Sanction No.: 1641
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 512 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 61.94982 Cubic Meter 0.516 31.96610712 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 42.922125 Cubic Meter 0.1236 5.30517465 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 72.8181575 Cubic Meter 3.9 283.99081425 - - 0.18 13.10726835 - -
4 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 16.98 Square Meter 0.12 2.0376 - - 0.14 2.3772 - -
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 111.9545 Square Meter - - 0.05 5.597725 0.05 5.597725 - -
6 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 17.1039375 Cubic Meter 4.6 78.6781125 - - 0.68 11.6306775 - -
7 Masonry Brick Work (AR0603c) : Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 2.407725 Cubic Meter 2.96 7.126866 - - 1.05 2.52811125 0.35 0.84270375
Total Qty 409.10467452 35.2409821 5.597725 0.84270375
Rate Per Man Day 462 562 512 612
Total Amount 189006.35962824 19805.4319402 2866.0352 515.734695
Total Labour Amount (in Rs.): 212193.56146344