Labour Statement

State: Odisha District: Balasore Block: Basta Gram Panchayat: Natakata
Work Code: OD/346/3301/116130/392386/00065285 (CONSTRUCTION OF CC ROAD FROM MAHALSAHI TO BENUDHAR BHADRA HOUSE)
Project Category: Road
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Basta Bill Status: Final Bill
Proposal Date: 08-06-2021 Date of Commencement: 25-11-2025
Date of Completion: 15-12-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: BHAGYALAXMI MOHANTA
Administrative Approval Details
Approval No.: OD/346/3301/116130/392386/00065285/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3301/116130/392386/00065285/TS
Fund Sanction No.: 9114
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
Rs. 462 Rs. 562 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0101a1) : Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 4.793751072 Cubic Meter 0.35 1.6778128752 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 14.607362863745 Cubic Meter 0.1236 1.8054700499589 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 21.870622063745 Cubic Meter 3.9 85.295426048605 - - 0.18 3.9367119714741
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 15.842116927745 Cubic Meter 4.6 72.873737867627 - - 0.68 10.772639510867
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 31.45509774 Square Meter - - 0.05 1.572754887 0.05 1.572754887
Total Qty 161.65244684139 16.282106369341 1.572754887
Rate Per Man Day 462 562 512
Total Amount 74683.430440723 9150.5437795695 805.250502144
Total Labour Amount (in Rs.): 84639.224722436